Completed

Jamtha, Nagpur 441122 |Promoter: Sadesh Realty Builders LLP

5 Mar 2019Registered with MahaRERA
30 Sep 2023Promised completion
29 Sep 2024Revised completionPushed back 1 year
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Completed
Land area for this project
22,245 sq m (2,39,439 sq ft)
Permissible built-up area
19,739 sq m (2,12,466 sq ft)
Sanctioned built-up area
0 sq m (0 sq ft)
Recreational open space
2,246 sq m (24,179 sq ft)
Address
Kh No 158-1, 158-2, Waradha Road, Near Vca GroundPIN 441122
Designated bank account
Axis Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 21.14580, 79.08815
Divine City is at latitude 21.14580, longitude 79.08815.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year

The latest completion date on record passed 2 years and 1 month ago.

Registered
5 Mar 2019
Promised
30 Sep 2023
Revised
29 Sep 2024

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P505000198105 Mar 201930 Sep 202329 Sep 2024Sadesh Realty Builders LLPProject page

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Building

  • ExcavationNot applicable
  • Basement (if any)Not applicable
  • Podiums (if any)Not applicable
  • PlinthNot applicable
  • Stilt FloorNot applicable
  • Slabs of Super StructureNot applicable
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
  • Sanitary Fittings within the flats / premisesNot applicable
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Common areas and amenities

  • Internal Roads & FootpathsTOTAL AREA 6397.64 SQ MTRS99%
  • Water SupplyHDPE OR DI100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)STP100%
  • Storm Water DrainsRCC100%
  • Landscaping & Tree PlantingTo be Updated by promoter42%
  • Street LightingRCC POLE OR MS POLE92%
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterSTP98%
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingRCC100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

18 documents held by Deedo, 110 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Occupancy / completion certificate (5)

  • Occupancy / completion certificate1 Jun 2024ViewSource
  • Occupancy / completion certificate18 Nov 2024ViewSource
  • Occupancy / completion certificate18 Nov 2024ViewSource
  • Occupancy / completion certificate18 Nov 2024ViewSource
  • Occupancy / completion certificate12 Feb 2025ViewSource

Form 1 (3)

Show all 128 documentsShow fewer documents

Form 1 (3)

Form 2 (5)

Form 4

Other (2)

Document library

  • Declaration in FORM B158_FORM B.pdf · uploaded 25 Feb 2019Source
  • Details of encumbrances158_TITLE DECLARATION.pdf · uploaded 25 Feb 2019Source
  • Proforma of Allotment letter158_ALLOTMENT LETTER.pdf · uploaded 25 Feb 2019Source
  • Proforma of Allotment letter158_AGREEMENT TO SALE.pdf · uploaded 25 Feb 2019Source
  • Copy of the legal title report158_TITLE SERACH REPORT.pdf · uploaded 25 Feb 2019Source
  • Commencement Certificates / NA Order for plotted development158_commencement.pdf · uploaded 25 Feb 2019Source
  • Copy of Layout Approval (in case of layout)158_SANCTION MAP.pdf · uploaded 25 Feb 2019Source
  • Building Plan Approval (IOD)158_SANCTION MAP.pdf · uploaded 25 Feb 2019Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)158_ENGG CERTIFICATE.pdf · uploaded 25 Feb 2019Source
  • Form 2AKh 158 Form 2A.pdf · uploaded 19 Jun 2019Source
  • Commencement Certificates / NA Order for plotted development2-LETTER KH NO -158-1 AND 2 DTD 02-12-2022.pdf · uploaded 4 Feb 2023Source
  • Copy of Layout Approval (in case of layout)4-REVISED LAYOUT PLAN KH NO 158-1 2 NA PURPOSE ONLY DTD 02-12-2022_compressed.pdf · uploaded 4 Feb 2023Source
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 FY 19-20 158.pdf · uploaded 13 Apr 2023Source
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)01 Form 5 D-1 F Y 19-20.pdf · uploaded 21 Apr 2023Source
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)02 Form 5 D-1 F Y 20-21.pdf · uploaded 21 Apr 2023Source
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)03 Form 5 D-1 F Y 21-22.pdf · uploaded 21 Apr 2023Source
  • Declaration in FORM BDivine City Declaration Form B.pdf · uploaded 15 Oct 2023Source
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 DIVINE CITY FY 22-23.pdf · uploaded 15 Oct 2023Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 DIVINE CITY 31-3-23.pdf · uploaded 15 Oct 2023Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 DIVINE CITY 30-9-23.pdf · uploaded 15 Oct 2023Source
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentRL 563.pdf · uploaded 1 Jun 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Divine City Form 1 March 2019.pdf · uploaded 18 Jul 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Divine City Form 1 June 2019.pdf · uploaded 18 Jul 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Divine City Form 1 Sep 2019.pdf · uploaded 18 Jul 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Devine City Form 1 Dec 2019.pdf · uploaded 18 Jul 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Divine City Form 1 March 2020.pdf · uploaded 18 Jul 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Divine City Form 1 June 2020.pdf · uploaded 18 Jul 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Dvine City Form 1 Sep 2020.pdf · uploaded 18 Jul 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Devine City Form 1 Dec 2020.pdf · uploaded 18 Jul 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Divine City Form 1 March 2021.pdf · uploaded 18 Jul 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Divine City Form 1 June 2021.pdf · uploaded 18 Jul 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Divine City Form 1 Sep 2021.pdf · uploaded 18 Jul 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Devine City Form 1 Dec 2021.pdf · uploaded 18 Jul 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Divine City Form 1 March 2022.pdf · uploaded 18 Jul 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Divine City Form 1 June 2022.pdf · uploaded 18 Jul 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Divine City Form 1 Sep 2022.pdf · uploaded 18 Jul 2024Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City Form 1 Dec 2022.pdf · uploaded 18 Jul 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Divine City Form 1 June 2023.pdf · uploaded 18 Jul 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Divine City Form 1 Dec 2023.pdf · uploaded 18 Jul 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Divine City Form 1 Dec 2023.pdf · uploaded 18 Jul 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Divine City Form 1 March 2024.pdf · uploaded 18 Jul 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Divine City Form 1 June 2024.pdf · uploaded 18 Jul 2024Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City_Form-2-Engineers Certificate_June-19---------2.pdf · uploaded 23 Jul 2024Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City_Form-2-Engineers Certificate_Sep-19---------3.pdf · uploaded 23 Jul 2024Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City_Form-2-Engineers Certificate_Dec-19---------4.pdf · uploaded 23 Jul 2024Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City_Form-2-Engineers Certificate_Mar-20---------5.pdf · uploaded 23 Jul 2024Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City_Form-2-Engineers Certificate_June-20---------6.pdf · uploaded 23 Jul 2024Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City_Form-2-Engineers Certificate_Sep-20--------7.pdf · uploaded 23 Jul 2024Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City_Form-2-Engineers Certificate_Dec-20---------8.pdf · uploaded 23 Jul 2024Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City_Form-2-Engineers Certificate_Mar-21---------9.pdf · uploaded 23 Jul 2024Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City_Form-2-Engineers Certificate_June-21-------10.pdf · uploaded 23 Jul 2024Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City_Form-2-Engineers Certificate_Sep-21------11.pdf · uploaded 23 Jul 2024Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City_Form-2-Engineers Certificate_Dec-21---------12.pdf · uploaded 23 Jul 2024Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City_Form-2-Engineers Certificate_Mar-22--------13.pdf · uploaded 23 Jul 2024Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City_Form-2-Engineers Certificate_June-22---------14.pdf · uploaded 23 Jul 2024Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City_Form-2-Engineers Certificate_Sep-22---------15.pdf · uploaded 23 Jul 2024Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City_Form-2-Engineers Certificate_Dec-22---------16.pdf · uploaded 23 Jul 2024Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City_Form-2-Engineers Certificate_Mar-23---------17.pdf · uploaded 23 Jul 2024Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City_Form-2-Engineers Certificate_June-23----------18.pdf · uploaded 23 Jul 2024View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City_Form-2-Engineers Certificate_Sep-23--------19.pdf · uploaded 23 Jul 2024View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City_Form-2-Engineers Certificate_Dec-23--------20.pdf · uploaded 23 Jul 2024View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City_Form-2-Engineers Certificate_Mar-24---------21.pdf · uploaded 23 Jul 2024View
  • Form 2ADivine City_Form-2A_Mar-19.pdf · uploaded 23 Jul 2024Source
  • Form 2ADivine City_Form-2A_Mar-20.pdf · uploaded 23 Jul 2024Source
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Divine City_Form-2A_Mar-21.pdf · uploaded 23 Jul 2024Source
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Divine City_Form-2A_Mar-22.pdf · uploaded 23 Jul 2024Source
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Divine City_Form-2A_Mar-23.pdf · uploaded 23 Jul 2024Source
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Divine City_Form-2A_Mar-24.pdf · uploaded 23 Jul 2024Source
  • Disclosure of sold/ booked inventorySOLD_UNSOLD_INVENTORY_Divine City_Mar-21--1.pdf · uploaded 23 Jul 2024Source
  • Disclosure of sold/ booked inventorySOLD_UNSOLD_INVENTORY_Divine City_June-21----2.pdf · uploaded 23 Jul 2024Source
  • Disclosure of sold/ booked inventorySOLD_UNSOLD_INVENTORY_Divine City_Mar-21--1.pdf · uploaded 23 Jul 2024Source
  • Disclosure of sold/ booked inventorySOLD_UNSOLD_INVENTORY_Divine City_June-21----2.pdf · uploaded 23 Jul 2024Source
  • Disclosure of sold/ booked inventorySOLD_UNSOLD_INVENTORY_Divine City_Sep-21----3.pdf · uploaded 23 Jul 2024Source
  • Disclosure of sold/ booked inventorySOLD_UNSOLD_INVENTORY_Divine City_Dec-21------4.pdf · uploaded 23 Jul 2024Source
  • Disclosure of sold/ booked inventorySOLD_UNSOLD_INVENTORY_Divine City_Mar-22-----5.pdf · uploaded 23 Jul 2024Source
  • Disclosure of sold/ booked inventorySOLD_UNSOLD_INVENTORY_Divine City_June-22----6.pdf · uploaded 23 Jul 2024Source
  • Disclosure of sold/ booked inventorySOLD_UNSOLD_INVENTORY_Divine City_Sep-22----7.pdf · uploaded 23 Jul 2024Source
  • Disclosure of sold/ booked inventorySOLD_UNSOLD_INVENTORY_Divine City_Dec-22-----8.pdf · uploaded 23 Jul 2024Source
  • Disclosure of sold/ booked inventorySOLD_UNSOLD_INVENTORY_Divine City_Mar-23-----9.pdf · uploaded 23 Jul 2024Source
  • Disclosure of sold/ booked inventorySOLD_UNSOLD_INVENTORY_Divine City_June-23----10.pdf · uploaded 23 Jul 2024Source
  • Disclosure of sold/ booked inventorySOLD_UNSOLD_INVENTORY_Divine City_Sep-23----11.pdf · uploaded 23 Jul 2024Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Divine City_Form-2-Engineers Certificate_June-24.pdf · uploaded 24 Jul 2024View
  • Disclosure of sold/ booked inventorySOLD_UNSOLD_INVENTORY_Divine City_Dec-23.pdf · uploaded 25 Jul 2024Source
  • Disclosure of sold/ booked inventorySOLD_UNSOLD_INVENTORY_Divine City_Mar-24.pdf · uploaded 25 Jul 2024Source
  • Disclosure of sold/ booked inventorySOLD_UNSOLD_INVENTORY_Divine City_June-24.pdf · uploaded 25 Jul 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1.pdf · uploaded 26 Oct 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development02-02-2023-1170.pdf · uploaded 18 Nov 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development02-02-2023-1170.pdf · uploaded 18 Nov 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development08-05-2023-511.pdf · uploaded 18 Nov 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development14-09-2023-1006.pdf · uploaded 18 Nov 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development08-05-2023-511.pdf · uploaded 18 Nov 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development14-09-2023-1006.pdf · uploaded 18 Nov 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Divine City Form 5.pdf · uploaded 7 Dec 2024Source
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development1.pdf · uploaded 19 Dec 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development2.pdf · uploaded 19 Dec 2024Source
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development3.pdf · uploaded 19 Dec 2024Source
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development4.pdf · uploaded 19 Dec 2024Source
  • Architect’s Certificate on Completion of Project (Form 4)FORM-4.pdf · uploaded 19 Dec 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC.pdf · uploaded 12 Feb 2025View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFORM-4.pdf · uploaded 12 Feb 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Divine City.pdf · uploaded 22 Apr 2025Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Divine City.pdf · uploaded 22 Apr 2025Source
  • Disclosure of sold/ booked inventorySold Divine City.pdf · uploaded 22 Apr 2025Source

Promoter documents

  • Declaration Form B158_FORM B.pdf · uploaded 25 Feb 2019Source
  • Legal Title report158_TITLE SERACH REPORT.pdf · uploaded 25 Feb 2019Source
  • Declaration Form BDivine City Declaration Form B.pdf · uploaded 15 Oct 2023Source

Technical documents

  • NA Order for Plotted Development158_SANCTION MAP.pdfSource
  • Layout Approval158_SANCTION MAP.pdfSource
  • Layout Approval4-REVISED LAYOUT PLAN KH NO 158-1 2 NA PURPOSE ONLY DTD 02-12-2022_compressed.pdfSource

Proforma allotment letter

  • Proforma allotment letter158_ALLOTMENT LETTER.pdfSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Jamtha, Nagpur (Rural) taluka

Survey, CTS, gat or plot numbers

1582KH NO 1581

As published on MahaRERA's project page

KH NO 158-1, 158-2

Boundaries

North
Khasara No 156-1
South
Khasara No 161
East
24 Mtrs Wide Road
West
Khasara No 159 P

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectUmesh Lamge & Associates—
Chartered accountantO P Tiwari—
EngineerKrishna T Turai—
OtherA D Buradkar—
Real Estate AgentAmjad Rahmatullah Khan—
Real Estate AgentAnand B Salve—
Real Estate AgentIrfan Qasim Shaikh—
Real Estate AgentKameel Raza Abdul Qadeer—
Show all 40 professionalsShow fewer professionals
RoleNameRegistration no.
Real Estate AgentNaved Juned Siddiqui—
Real Estate AgentNitesh Subhashrao Tekade—
Real Estate AgentOshian Realtors India Private Limited—
Real Estate AgentPramod Jangluji Kamble—
Real Estate AgentPriya Sunil Babde—
Real Estate AgentRajesh Jaisingh Salkotia—
Real Estate AgentRavi Wankhede—
OtherSanjay Baniya—
Real Estate AgentShabbir Aslam Khan—
Real Estate AgentShadanan Hemraj Ashtankar—
Real Estate AgentSirajul Hasan Wajid Hussain Siddiqui—
Real Estate AgentVaibhav Chandrashekhar Thombare—
OtherVindevasini Construction—
Real Estate AgentVinod Purushottam Ashtankar—
Real Estate AgentVirag Dayashankar Meshram—
Registered real estate agentAmjadrahmatullah KhanA50500007822
Registered real estate agentAnandb SalveA51500025210
Registered real estate agentIrfanqasim ShaikhA50500008827
Registered real estate agentKameel Raza Abdul QadeerA50500008607
Registered real estate agentNavedjuned SiddiquiA50500009683
Registered real estate agentNiteshsubhashrao TekadeA50300022974
Registered real estate agentOshian Realtors India Private LimitedA50500010897
Registered real estate agentPramodjangluji KambleA50900029337
Registered real estate agentPriyasunil BabdeA50500025138
Registered real estate agentRajeshjaisingh SalkotiaA51500026414
Registered real estate agentRavi WankhedeA51500025127
Registered real estate agentShabbiraslam KhanA50500009561
Registered real estate agentShadananhemraj AshtankarA50500035781
Registered real estate agentSirajul Hasanwajid Hussain SiddiquiA50500022475
Registered real estate agentVaibhavchandrashekhar ThombareA50500035693
Registered real estate agentVinodpurushottam AshtankarA50500035752
Registered real estate agentViragdayashankar MeshramA50500023045

Source: MahaRERA project page. Contact details are not shown.