Savana Phase I

Completed

Borivali, Mumbai Suburban 400101 |Promoter: Simba Properties LLP

29 Nov 2019Registered with MahaRERA
30 Jun 2023Promised completion
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Completed
Buildings
1
Land area for this project
820 sq m (8,826 sq ft)
Permissible built-up area
1,047 sq m (11,270 sq ft)
Sanctioned built-up area
955 sq m (10,280 sq ft)
Address
809A/1/1/6 AND 809A/1/1/7, 120 Feet Road, Thakur Village, Kandivali EastPIN 400101
Designated bank account
Hdfc Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Savana Phase I is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Jun 2023

The latest completion date on record passed 3 years and 4 months ago.

Registered
29 Nov 2019
Promised
30 Jun 2023

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5180002309929 Nov 201930 Jun 2023—Simba Properties LLPProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Savana Commercial3—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered000023
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Savana Commercial

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplySupply by MCGM0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Provision for connection to common STP0%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

66 documents held by Deedo, 78 filings listed on MahaRERA's project page

Other (65)

Show all 144 documentsShow fewer documents

Other (65)

Registration certificate

Document library

  • Commencement Certificates / NA Order for plotted development20191111 VH Plinth CC.pdf · uploaded 12 Nov 2019View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate-1.pdf · uploaded 13 Nov 2019View
  • OtherREGISTERED AGREEMENT FOR SALE - PART 1.pdf · uploaded 13 Nov 2019View
  • OtherREGISTERED AGREEMENT FOR SALE - PART 2.pdf · uploaded 13 Nov 2019View
  • Declaration in FORM BDeclaration Form B-1.pdf · uploaded 13 Nov 2019View
  • Copy of Layout Approval (in case of layout)Layout Approval letter.pdf · uploaded 21 Nov 2019View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)PHASE 1 ARCHITECT CERTIFICATE.pdf · uploaded 22 Nov 2019View
  • Proforma of Allotment letterAllotment Letter Phase 1.pdf · uploaded 22 Nov 2019View
  • Building Plan Approval / NA Order for plotted developmentBUILDING APPROVAL LETTER-1.pdf · uploaded 22 Nov 2019View
  • Proforma of Allotment letterDeclaration-Agreement for sale Phase I-1.pdf · uploaded 22 Nov 2019View
  • Copy of Layout Approval (in case of layout)Plans (1) (1).pdf · uploaded 27 Nov 2019View
  • Details of encumbrancesSPLLP Declaration.pdf · uploaded 27 Nov 2019View
  • Copy of the legal title reportReport on Title.pdf · uploaded 27 Nov 2019View
  • Proforma of Allotment letterAgreement Phase 1.pdf · uploaded 27 Nov 2019View
  • Copy of Layout Approval (in case of layout)19112710601 SAVANA PHASES.pdf · uploaded 27 Nov 2019View
  • Proforma of Allotment letterallotment letter phase 1 180220.pdf · uploaded 18 Feb 2020View
  • Proforma of Allotment letterAgreement Phase 1 180220.pdf · uploaded 18 Feb 2020View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A RERA.pdf · uploaded 11 Mar 2020View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)RERA Form 2 Phase 1 60820.pdf · uploaded 10 Aug 2020View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1Phase1Ending31March20.pdf · uploaded 8 Sep 2020View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1Phase1Ending30june20.pdf · uploaded 8 Sep 2020View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 3 Phase 1 300620.pdf · uploaded 19 Sep 2020View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form No 5 Phase 1.pdf · uploaded 1 Oct 2020View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1Phase1Ending30Sept20.pdf · uploaded 3 Nov 2020View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Phase 1 as on 300620.pdf · uploaded 3 Nov 2020View
  • Details of encumbrancesNo Encumberance Certificate Revised_compressed.pdf · uploaded 9 Dec 2020View
  • Declaration in FORM BDeclaration Form B_Revised.pdf · uploaded 30 Dec 2020View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1Phase1Ending31Dec20.pdf · uploaded 21 Jan 2021View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Phase 1 311220 compressed.pdf · uploaded 22 Jan 2021View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1Phase1Ending31MAR2021.pdf · uploaded 19 Apr 2021View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Phase I compressed.pdf · uploaded 4 May 2021View
  • Disclosure of sold/ booked inventoryUnit Details - Phase I.PDF · uploaded 4 Jun 2021View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Phase I.pdf · uploaded 1 Jul 2021View
  • Declaration about Commencement CertificateRERA Form D for further persmission received.pdf · uploaded 12 Jul 2021View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 2 Phase I.pdf · uploaded 4 Aug 2021View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Phase I.pdf · uploaded 4 Aug 2021View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 SAVANA Phase I_compressed.pdf · uploaded 16 Nov 2021View
  • Disclosure of sold/ booked inventoryUnit Sold_Unsold Phase I.pdf · uploaded 16 Nov 2021View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 SAVANA Phase_I_compressed.pdf · uploaded 19 Nov 2021View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Phase I_compressed.pdf · uploaded 9 Feb 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Phase I_compressed.pdf · uploaded 9 Feb 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA Form 1 - Phase I_compressed.pdf · uploaded 20 May 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)RERA Form 2 - Phase I_compressed.pdf · uploaded 20 May 2022View
  • Other – Technical2335003_FurtherCC_signed.pdf · uploaded 26 Jul 2022View
  • Building Plan Approval / NA Order for plotted development3rd Amended IOD.pdf · uploaded 30 Jul 2022View
  • Building Plan Approval / NA Order for plotted development3rd Amended IOD Drawings Part 1.pdf · uploaded 30 Jul 2022View
  • Building Plan Approval / NA Order for plotted development3rd Amended IOD Drawings Part 2.pdf · uploaded 30 Jul 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA Form 1 - Phase I.pdf · uploaded 5 Aug 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)RERA Form 1 - Phase II.pdf · uploaded 5 Aug 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)RERA Form 2 - Phase I.pdf · uploaded 5 Aug 2022View
  • Disclosure of sold/ booked inventoryUnit Details - Phase I.pdf · uploaded 12 Aug 2022View
  • Commencement Certificates / NA Order for plotted developmentFurther CC TA 29 TB 34.pdf · uploaded 18 Aug 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A RERA SAVANA.pdf · uploaded 25 Aug 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 Savana Phase I.pdf · uploaded 15 Oct 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Phase I.pdf · uploaded 31 Oct 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Phase I.pdf · uploaded 4 Nov 2022View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentShop OC Certificate.pdf · uploaded 22 Dec 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 SAVANA Phase I_compressed.pdf · uploaded 22 Dec 2022View
  • Status of Formation of Legal Entity (Society/Co Op etc.)savan shops society name reservation.pdf · uploaded 20 Jan 2023View
  • Disclosure of sold/ booked inventoryUnit Sold - Unsold Phase I Dec 22.pdf · uploaded 20 Jan 2023View
  • Proforma of Agreement for sale1673072761918CKV8478240.pdf · uploaded 20 Jan 2023View
  • Proforma of Agreement for saleRegistered Agreement for Sale Part 1.pdf · uploaded 20 Jan 2023View
  • Proforma of Agreement for saleAFS with Customer.pdf · uploaded 24 Jan 2023View
  • Architect’s Certificate on Completion of Project (Form 4)Form 4 Maha RERA CERTIFICATE for Shop OC 22112022.pdf · uploaded 24 Jan 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Simba Savana Phase I RERA No P51800023099 FY2023.pdf · uploaded 27 Sep 2023View

Promoter documents

  • Declaration Form BDeclaration Form B-1.pdf · uploaded 13 Nov 2019View
  • Legal Title reportReport on Title.pdf · uploaded 27 Nov 2019View
  • Declaration Form BDeclaration Form B_Revised.pdf · uploaded 30 Dec 2020View

Technical documents

  • Building Plan ApprovalBUILDING APPROVAL LETTER-1.pdfView
  • Layout ApprovalPlans (1) (1).pdfView
  • Layout Approval19112710601 SAVANA PHASES.pdfView
  • Layout ApprovalLayout Approval letter.pdfView
  • Building Plan Approval3rd Amended IOD.pdfView
  • Building Plan Approval3rd Amended IOD Drawings Part 1.pdfView
  • Building Plan Approval3rd Amended IOD Drawings Part 2.pdfView

Other legal documents

  • OtherREGISTERED AGREEMENT FOR SALE - PART 1.pdfView
  • OtherREGISTERED AGREEMENT FOR SALE - PART 2.pdfView

Proforma allotment letter

  • Proforma allotment letterDeclaration-Agreement for sale Phase I-1.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Borivali, Borivali taluka

Survey, CTS, gat or plot numbers

809A/1/1/6809A/1/1/7

As published on MahaRERA's project page

809A/1/1/6 AND 809A/1/1/7

Boundaries

North
by 27 45 Mtr wode DP Road
South
CTS No 809A 1 1 8 and 809A 1 1 9
East
36 60 Mtr wide DP Road
West
CTS No 809-A 1 1 5 part

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectKetan H Mehta—
ArchitectM/s 4Site Architects—
Chartered accountantRsva & Co—
EngineerMep Consulting Engineers—
OtherACC India Private Limited—
OtherPunit Infracon Pvt Ltd—
Other——

Source: MahaRERA project page. Contact details are not shown.

Data through12 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology