Skip to content

Lashkaria Indrasukh

Active

Ambivali, Mumbai Suburban 400053 |Promoter: Lashkaria Housing & infrastructure Limited

8 Sep 2023Registered with MahaRERA
31 Dec 2028Promised completion
3Buildings
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Active
Buildings
3
Land area for this project
3,187 sq m (34,305 sq ft)
Permissible built-up area
10,323 sq m (1,11,121 sq ft)
Sanctioned built-up area
10,323 sq m (1,11,121 sq ft)
Planning authority
MCGM
Address
831/14, Four Bungalows Road, Andheri WestPIN 400053
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Lashkaria Indrasukh is at latitude 0.00000, longitude 0.00000.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2028

Registered
8 Sep 2023
Promised
31 Dec 2028

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P518000524718 Sep 202331 Dec 2028—Lashkaria Housing & infrastructure LimitedProject page

3 buildings

Buildings and wings named in the registration

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotalAllotted 2WAllotted 4W
Lashkaria Indrasukh - A WingClosed/Covered22720094220
Lashkaria Indrasukh - A WingOpen Space0000000
Lashkaria Indrasukh - B WingClosed/Covered21720093220
Lashkaria Indrasukh - B WingOpen Space0000000
Lashkaria Indrasukh - C WingClosed/Covered21710092220
Lashkaria Indrasukh - C WingOpen Space0000000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Lashkaria Indrasukh - A Wing

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)90%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure95%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
  • Sanitary Fittings within the flats / premises70%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Lashkaria Indrasukh - B Wing

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)90%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure95%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
  • Sanitary Fittings within the flats / premises70%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Lashkaria Indrasukh - C Wing

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)90%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure95%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
  • Sanitary Fittings within the flats / premises70%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyWill be provided as per norms.0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Will be provided as per norms.0%
  • Storm Water DrainsWill be provided as per norms.0%
  • Landscaping & Tree PlantingWill be provided as per norms.0%
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterWill be provided as per norms.0%
  • Solid Waste Management And DisposalWill be provided as per norms.0%
  • Water conservation /Rain water harvestingWill be provided as per norms.0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsWill be provided as per norms.0%
  • Electrical meter room, sub-station, receiving stationWill be provided as per norms.0%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

83 documents held by Deedo, 69 filings listed on MahaRERA's project page

Encumbrance details (2)

Other (42)

Show all 152 documentsShow fewer documents

Other (42)

Title report

Commencement certificate (3)

Form B

Allotment letter (2)

Form 1 (10)

Form 2A (2)

Form 5

Form 2 (4)

Registration certificate

Layout plan (13)

Building plan

Document library

  • a Details of encumbrances concerned to FinanceNo Encumbrance Self Declaration Letter.pdf · uploaded 13 May 2023View
  • b Details of encumbrances concerned to LegalNo Encumbrance Self Declaration Letter.pdf · uploaded 13 May 2023View
  • Building Plan Approval / NA Order for plotted developmentIOD.pdf · uploaded 13 May 2023View
  • CERSAI detailsCersai Declaration Letter.pdf · uploaded 13 May 2023View
  • Copy of the legal title reportLEGAL TITLE REPORT_0001 (1).pdf · uploaded 19 Jun 2023View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat - A- Declaration about seperate bank account.pdf · uploaded 19 Jun 2023View
  • Copy of Layout Approval (in case of layout)1745 IOD Drawing (Plan)_1-1.pdf · uploaded 19 Jun 2023View
  • Copy of Layout Approval (in case of layout)1745 IOD Drawing (Plan)_2-2.pdf · uploaded 19 Jun 2023View
  • Copy of Layout Approval (in case of layout)1745 IOD Drawing (Plan)_3-3.pdf · uploaded 19 Jun 2023View
  • Copy of Layout Approval (in case of layout)1745 IOD Drawing (Plan)_4-4.pdf · uploaded 19 Jun 2023View
  • Copy of Layout Approval (in case of layout)1745 IOD Drawing (Plan)_5-5.pdf · uploaded 19 Jun 2023View
  • Copy of Layout Approval (in case of layout)1745 IOD Drawing (Plan)_6-6.pdf · uploaded 19 Jun 2023View
  • Copy of Layout Approval (in case of layout)1745 IOD Drawing (Plan)_7-7.pdf · uploaded 19 Jun 2023View
  • Copy of Layout Approval (in case of layout)1745 IOD Drawing (Plan)_8-8.pdf · uploaded 19 Jun 2023View
  • Copy of Layout Approval (in case of layout)1745 IOD Drawing (Plan)_9-9.pdf · uploaded 19 Jun 2023View
  • Copy of Layout Approval (in case of layout)1745 IOD Drawing (Plan)_10-end.pdf · uploaded 19 Jun 2023View
  • Proforma of Agreement for saleFinal Lashkaria_Indrasukh_Flat_Agreement__Final.pdf · uploaded 21 Aug 2023View
  • Commencement Certificates / NA Order for plotted developmentCHE WS 1745 First CC (1).pdf · uploaded 21 Aug 2023View
  • Disclosure of Interest in Other Real Estate OrganizationsAnnexure - A - All Directors (2).pdf · uploaded 21 Aug 2023View
  • Declaration in FORM BFORM B -1_0001.pdf · uploaded 21 Aug 2023View
  • Deviation Report with respect to Allotment letterDeviation Report allotment Letter.pdf · uploaded 22 Aug 2023View
  • Deviation Report with respect to model copy of AgreementDeviation Report agreement.pdf · uploaded 22 Aug 2023View
  • Declaration about Commencement CertificateIndrasukh - CC Letter (1).pdf · uploaded 22 Aug 2023View
  • Proforma of Allotment letterFinal ALLOTMENT_LETTER_FINAL (1) (2).pdf · uploaded 22 Aug 2023View
  • Commencement Certificates / NA Order for plotted development2415542_FurtherCC_signed (1).pdf · uploaded 14 Mar 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 29 Nov 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 29 Nov 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 29 Nov 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 29 Nov 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 29 Nov 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)form 2A 23-24.pdf · uploaded 29 Nov 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form 5 23-24.pdf · uploaded 29 Nov 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 Sep 23.pdf · uploaded 29 Nov 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 Dec 23.pdf · uploaded 29 Nov 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 Mar 24.pdf · uploaded 29 Nov 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 Jun 24.pdf · uploaded 29 Nov 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 Sep 24.pdf · uploaded 29 Nov 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 11 Mar 2025View
  • Withdrawal Update Form 1form1 architect.pdf · uploaded 4 Mar 2026View
  • Withdrawal Update Form 2form 2.pdf · uploaded 4 Mar 2026View
  • Withdrawal Update Form 1Form1 Arch Certificate Indrasukh Jul Sep 25 Signed.pdf · uploaded 5 Mar 2026View
  • Withdrawal Update Form 2Form2_Engg_Certificate_Indrasukh__Jul-Sep_25_.pdf · uploaded 5 Mar 2026View
  • Withdrawal Update Form 1Form1 Arch Certificate Indrasukh Oct Dec 25 Signed.pdf · uploaded 5 Mar 2026View
  • Withdrawal Update Form 2Form2 Engg Certificate Indrasukh Oct Dec 25.pdf · uploaded 5 Mar 2026View
  • Form 2A (FY 2025-2026)form 2A.pdf · uploaded 16 May 2026View
  • Withdrawal Update Form 1form 1.pdf · uploaded 16 May 2026View
  • Withdrawal Update Form 2form 2.pdf · uploaded 16 May 2026View
  • Withdrawal Update Form 1form 1.pdf · uploaded 16 May 2026View
  • Withdrawal Update Form 2form 2.pdf · uploaded 16 May 2026View
  • Withdrawal Update Form 1Form1 Arch Certificate Indrasukh Apr Jun 26.pdf · uploaded 16 Sep 2026View
  • Withdrawal Update Form 2Form2 Engg Certificate Indrasukh Apr Jun 26.pdf · uploaded 16 Sep 2026View

Promoter documents

  • Legal Title reportLEGAL TITLE REPORT_0001 (1).pdf · uploaded 19 Jun 2023View
  • Declaration Form BFORM B -1_0001.pdf · uploaded 21 Aug 2023View

Technical documents

  • Layout Approval1745 IOD Drawing (Plan)_1-1.pdfView
  • Layout Approval1745 IOD Drawing (Plan)_2-2.pdfView
  • Layout Approval1745 IOD Drawing (Plan)_3-3.pdfView
  • Layout Approval1745 IOD Drawing (Plan)_4-4.pdfView
  • Layout Approval1745 IOD Drawing (Plan)_5-5.pdfView
  • Layout Approval1745 IOD Drawing (Plan)_6-6.pdfView
  • Layout Approval1745 IOD Drawing (Plan)_7-7.pdfView
  • Layout Approval1745 IOD Drawing (Plan)_8-8.pdfView
  • Layout Approval1745 IOD Drawing (Plan)_9-9.pdfView
  • Layout Approval1745 IOD Drawing (Plan)_10-end.pdfView
  • Layout ApprovalPlans 1.pdfView
  • Layout ApprovalPlans 2.pdfView
  • Layout ApprovalPlans 3.pdfView
  • Building Plan ApprovalIOD.pdfView

Commencement certificates and NA orders

  • Commencement certificate / NA orderSource

Proforma allotment letter

  • Proforma allotment letterFinal ALLOTMENT_LETTER_FINAL (1) (2).pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Ambivali, Andheri taluka

Survey, CTS, gat or plot numbers

831/14

As published on MahaRERA's project page

831/14

Boundaries

North
Vishwajeet Society
South
9M Road Indra darshan society
East
18 Meter Road
West
Daswani CHS Ltd

Source: registration certificates and MahaRERA's project page, as stated there.

Data through12 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology