RERA projects in Ambivali

53 projects under 54 MahaRERA registrations, registered 2022–2026. 72% have a completion date extended beyond the one promised.

Locality
53RERA projects
54Registrationssome projects hold several
53Completion still due1 past their completion date
4 monthsMedian extension beyond promised date72% of registrations extended
0Regulatory casesnone on MahaRERA's lists
81Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20221
20237
20246
202519
202621

Projects in Ambivali

53 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Evershine Apartment No. 1Evershine Builders Private LimitedPM118000260248219 Oct 202630 Dec 2030—Not yet due0
72 EnclavePosh Homes Realty LLPPM118000260237816 Oct 202631 Dec 2030—Not yet due0
Ethics NilayaEthics RealtyPR11800026022269 Oct 202630 Jun 203030 Jun 2030Not yet due0
Vraj PremiereVraj Bvg Infrasheltors LLPPC11800026022199 Oct 202631 Dec 203031 Dec 2030Not yet due0
Mayfair AranyaMayfair HousingPR11800026014415 Aug 202631 Jul 203231 Jul 2032Not yet due0
Reform HeightsSkyline Reform LLPPM118000260113513 Jul 202631 Dec 203030 Apr 2031Extended 4 mo0
VantageRolland Spaces Private LimitedPM118101260115413 Jul 202630 Nov 203030 Mar 2031Extended 4 mo0
Kamla IrisKamla Shiv DeveloperPM118000260080515 Jun 202631 Dec 202830 Apr 2029Extended 4 mo0
Sudarshan EpitomeJagjit Estate And Development Co Pvt LtdPR118000260045918 May 202630 Dec 202930 Apr 2030Extended 4 mo0
Naman Fifty EightShree Naman Developers Private LimitedPM11800026003607 May 202631 Mar 203131 Mar 2031Not yet due0
PolarisPoonam Developers LLPPM11800026003667 May 202630 Jun 203130 Oct 2031Extended 4 mo0
Platinum VibePlatinum Urban Developers LLPPR118000260030730 Apr 202631 Dec 203030 Apr 2031Extended 4 mo0
Composite Building Rehab Wing A1A R Amboli Developers Private LimitedPR118000260019418 Apr 202631 Dec 202830 Apr 2029Extended 4 mo0
SkylineAimbitious Homes LLPPR118000260009815 Apr 202631 Dec 203030 Apr 2031Extended 4 mo0
Mk GloriaM K Shelters Private LimitedPM118000250285216 Mar 202631 Dec 202830 Apr 2029Extended 4 mo0
Spenta AntheaSpenta Vintage Private LimitedPR118000250284016 Mar 202631 Dec 202931 Dec 2029Not yet due0
New Ekta ChslShrimad Realtors LLPPR118000250270811 Mar 202631 Mar 202931 Jul 2029Extended 4 mo0
Rachanaa AaravyaTerraferma Developers LLPPR118000250269210 Mar 202630 Jun 202830 Oct 2028Extended 4 mo0
Avira Sai Shreeji Co-operative Housing Society LimitedAvira Realty Private LimitedPR11800025025622 Mar 202629 Dec 202929 Apr 2030Extended 4 mo0
Vann By AjmeraAjmera Realty And Infra India LtdPR118000250217827 Jan 202631 Jan 203131 May 2031Extended 4 mo0
Khandelwal AcropolisShree Krishna Sai Development CorporationPM118000250216022 Jan 202631 Dec 203030 Apr 2031Extended 4 mo0
Vraj Meridian-Nikunj ChslVraj Bvg Infrasheltors LLPPM118000250191829 Dec 202515 Dec 203015 Apr 2031Extended 4 mo0
SigniaHeadway Believe Realty LLPPR118000250189226 Dec 202531 Mar 203031 Jul 2030Extended 4 mo0
Khandelwal TattvaShree Krishna Sai Development CorporationPM118000250177915 Dec 202531 Dec 203030 Apr 2031Extended 4 mo0
Roswalt Shatataraka (Unit A) CHSLRoswalt Realty Private LimitedPR118000250137831 Oct 202528 Sep 202828 Jan 2029Extended 4 mo0

Other localities in Andheri

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Pranav Constructions Limited2 projects
  2. Shree Krishna Sai Development Corporation2 projects
  3. Vraj Bvg Infrasheltors LLP2 projects
  4. Adcore Developers LLP1 project
  5. Aimbitious Homes LLP1 project
  6. Ajmera Realty And Infra India Ltd1 project
  7. A R Amboli Developers Private Limited1 project
  8. Avira Realty Private Limited1 project
  9. Chandiwala Enterprises Private Limited1 project
  10. Disha Construction1 project
Data through19 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology