RERA projects in Ward Fnorth
177 projects under 183 MahaRERA registrations, registered 2017–2026. 18% have a completion date extended beyond the one promised.
Taluka
177RERA projects
183Registrationssome projects hold several
85Completion still due90 past their completion date
18 monthsMedian extension beyond promised date18% of registrations extended
4Regulatory caseson 4 projects
8Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 67 |
| 2018 | 9 |
| 2019 | 8 |
| 2020 | 7 |
| 2021 | 6 |
| 2022 | 13 |
| 2023 | 19 |
| 2024 | 17 |
| 2025 | 19 |
| 2026 | 10 |
Projects in Ward Fnorth
177 projects registered with MahaRERA in this taluka and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Krishna KunjEndemic Properties LLP | P51900078747 | 9 Jan 2025 | 30 Sep 2029 | — | Not yet due | 0 |
| Bellissimo Matunga -Tower 4 and Tower 5Lodha Developers Limited | P51900078502 | 19 Dec 2024 | 31 Mar 2030 | — | Not yet due | 0 |
| Hira HouseGoshar Alliance LLP | P51900078474 | 17 Dec 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| Godrej Horizon Phase IIIGodrej Projects Development Ltd | P51900078358 | 6 Dec 2024 | 30 Jun 2031 | — | Not yet due | 0 |
| Harsh SapphireHarsh Realty Builders & Developers | P51900078284 | 4 Dec 2024 | 31 Mar 2028 | — | Not yet due | 0 |
| Jade WisteriaJess Construction Private Limited | P51900078179 | 29 Nov 2024 | 31 Dec 2029 | — | Not yet due | 0 |
| Shree NiwasEndemic Properties LLP | P51900077703 | 22 Oct 2024 | 30 Jun 2029 | — | Not yet due | 0 |
| Madhoor AurumMadhoor Buildwell Private Limited | P51900077613 | 15 Oct 2024 | 30 Jun 2029 | — | Not yet due | 0 |
| Puje AnantaDalpatraj Pukhraj Jain | P51900077577 | 15 Oct 2024 | 31 Dec 2029 | — | Not yet due | 0 |
| Princecare AmaraaPrincecare Amaraa LLP | P51900077461 | 16 Aug 2024 | 31 May 2028 | — | Not yet due | 0 |
| Sanghvi OptimaSuparshwa Homes Private Limited | P51900077456 | 16 Aug 2024 | 31 May 2028 | — | Not yet due | 0 |
| Matunga SignetLodha Developers Limited | P51900077196 | 29 Jul 2024 | 30 Sep 2029 | — | Not yet due | 0 |
| Sugee SrushtiSugee Fifteen Developers LLP | P51900077195 | 29 Jul 2024 | 31 Oct 2027 | — | Not yet due | 0 |
| Tulsi HeritageBlue Stone Developers LLP | P51900066485 | 11 Jun 2024 | 30 Sep 2028 | — | Not yet due | 0 |
| Bellwether AmariBellwether Infrastructure LLP | P51900056402 | 31 May 2024 | 30 Jun 2027 | — | Not yet due | 0 |
| Madhav BhuvanMoonshine Homes | P51900056308 | 25 May 2024 | 30 Jun 2028 | — | Not yet due | 0 |
| Siddha Sky Phase VSejal Shakti Realtors LLP | P51900055793 | 22 Apr 2024 | 31 Mar 2030 | — | Not yet due | 0 |
| Ram Setu BhavanGbd Infracon LLP | P51900055203 | 11 Mar 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| Raheja Amaltis - Wing AK Raheja Corp Real Estate Private Limited | P51900054129 | 29 Dec 2023 | 30 Sep 2028 | — | Not yet due | 0 |
| Raheja Amaltis - Wing BK Raheja Corp Real Estate Private Limited | P51900054152 | 29 Dec 2023 | 30 Sep 2028 | — | Not yet due | 0 |
| Jade AcharyaRaghavendra Acharya & Others | P51900052681 | 20 Sep 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Lodha MatungaLodha Developers Limited | P51900052415 | 22 Aug 2023 | 30 Apr 2028 | — | Not yet due | 0 |
| Harsh TulipHarsh Developers & Infrastructure LLP | P51900051870 | 7 Jul 2023 | 31 Oct 2026 | — | Not yet due | 0 |
| Bellissimo MatungaLodha Developers Limited | P51900051742, P51900051743 | 27 Jun 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Jade SolitaireNational Happy Homes | P51900051442 | 14 Jun 2023 | 31 Mar 2027 | — | Not yet due | 0 |
Other talukas in Mumbai City
Most active promoters
By projects registered here, as named on MahaRERA.
- Macrotech Developers Limited9 projects
- Lodha Developers Limited6 projects
- Mhada4 projects
- Godrej Projects Development Ltd3 projects
- Newlook Constructions Pvt. Ltd3 projects
- Sahana-Sheth3 projects
- Aadi Shikhar LLP2 projects
- Adityaraj Developers2 projects
- Dosti Realty Ltd2 projects
- Endemic Properties LLP2 projects
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology