Sumer Armonia
Its promised completion date, Jun 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 10% of its units are booked.
Ward E, Maharashtra 400010 · Promoter: Victoria Iron & Metal Warehousing Private Limited
Its promised completion date, Jun 2025, has passed and MahaRERA does not show it completed
- This projectRegistered 4 Jun 2021, completion promised 30 Jun 2025, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51900029518
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51900029518 | 4 Jun 2021 | 30 Jun 2025 | 30 Jun 2025 | Victoria Iron & Metal Warehousing Private Limited | Project page |
Documents48
1 document held by Deedo, 47 filings listed on MahaRERA's project page
Finance
- PAN CardVICTORIA PANCARD.pdf · uploaded 19 May 2021Source
Legal
Migrated
- 1 PAN CardVICTORIA PANCARD.pdf · uploaded 19 May 2021Source
- 1 Details of encumbrancesENCUMBRANCE.pdf · uploaded 19 May 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCS 448 Zero FSI FirstCC.pdf · uploaded 19 May 2021Source
- 1 Declaration in FORM BPROMOTER FORM B VICTORIA.pdf · uploaded 19 May 2021Source
Show all 48 documentsShow fewer documents
Migrated
- 1 Building Plan Approval / NA Order for plotted developmentIOD - sumer armonia.pdf · uploaded 26 May 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Sumer Armonia.pdf · uploaded 26 May 2021Source
- 1 Proforma of Allotment letterAFS - Armonia - Fp - Approved by vatsal sir.pdf · uploaded 26 May 2021Source
- 1 Copy of the legal title reportRERA Title Certificate- 270521.pdf · uploaded 28 May 2021Source
- 1 Copy of Layout Approval (in case of layout)PLAN_compressed (1).pdf · uploaded 28 May 2021Source
- 2 Building Plan Approval / NA Order for plotted developmentPLAN_compressed (1).pdf · uploaded 28 May 2021Source
- 2 Proforma of Allotment letterallotment letter sample _victoria.pdf · uploaded 28 May 2021Source
- 1 Declaration about Commencement CertificateSumer Armonia.pdf · uploaded 22 Jul 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sumer Armonia.pdf · uploaded 25 Aug 2021Source
- 1 Disclosure of sold/ booked inventorySold Unsold details- Sumer Armonia.pdf · uploaded 20 Sep 2021Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sumer Armonia Form 1.pdf · uploaded 20 Apr 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Sumer Armonia June 2021_compressed.pdf · uploaded 20 Apr 2022Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Sumer Armonia Sept 2021_compressed.pdf · uploaded 20 Apr 2022Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Sumer Armonia Dec 2021_compressed.pdf · uploaded 20 Apr 2022Source
- 1 CERSAI detailsSumer Armonia.pdf · uploaded 20 Apr 2022Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Sumer Armonia 30th June 2021.pdf · uploaded 20 Apr 2022Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Sumer Armonia 30th September 2021.pdf · uploaded 20 Apr 2022Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Sumer Armonia 31st December 2021.pdf · uploaded 20 Apr 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 of Sumer Armonia FY 2021-22.pdf · uploaded 1 Oct 2022Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)SUMER ARMONIA.pdf · uploaded 6 Dec 2022Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sumer Armonia.pdf · uploaded 4 Jan 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Sumer Armonia March 2022.pdf · uploaded 29 Apr 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Sumer Armonia June 2022.pdf · uploaded 29 Apr 2023Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Sumer Armonia as on Sept 2022.pdf · uploaded 29 Apr 2023Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 31st March 2022.pdf · uploaded 29 Apr 2023Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Sumer Armonia June 22.pdf · uploaded 29 Apr 2023Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3- Sumer Armonia as on Sept 2022.pdf · uploaded 29 Apr 2023Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)7 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf · uploaded 2 Apr 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)4 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 16 Jul 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)6 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 16 Jul 2024Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)8 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf · uploaded 16 Jul 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)5 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 15 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)7 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 15 Feb 2025Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsCTS No. 448
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK108 units in all
- Address
- CTS No. 448, Champsi Bhimji Road, MazgaonPIN 400010
- Designated bank account
- 154
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- 18 meter wide champsi bhimji road
- South
- CTS No - 449
- East
- CTS No - 446
- West
- 6 meter wide internal road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking108 units
11 of 108 units booked (10%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 46.27 sq m · 498 sq ft | 56 | 5 |
| 2BHK | 55.74 sq m · 600 sq ft | 52 | 6 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Aakar Architects & Consultants Pvt. Ltd | — |
| Chartered accountant | Rutuja Narsingh& Associates | — |
| Engineer | JW Consultants LLP | — |
| Engineer | SK Consultants & Engineers | — |
| Other | RERA Easy | — |
Source: MahaRERA project page. Contact details are not shown.