RERA projects in Ausa (M Cl)

2 projects under 2 MahaRERA registrations, registered 2024–2025. 50% have a completion date extended beyond the one promised.

Locality
2RERA projects
2Registrations
2Completion still due0 past their completion date
4 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
8Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20241
20251

Projects in Ausa (M Cl)

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Sita Vihar -1North West InfraP5240007970620 Mar 202531 Dec 202931 Dec 2029Not yet due0
Venkatesh ApartmentMJP Builders & DevelopersP524000769129 Jul 202431 Dec 202730 Apr 2028Extended 4 mo0

Other localities in Ausa

Most active promoters

By projects registered here, as named on MahaRERA.

  1. MJP Builders & Developers1 project
  2. North West Infra1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology