The Rudra Square

Completed

Pimprala, Jalgaon 425001 |Promoter: Sunil Ramnarayan Mantri

8 May 2019Registered with MahaRERA
30 Jun 2023Promised completion
1Building
28Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Completed
Buildings
1
Unit types
2BHK, Shop28 units in all
Land area for this project
585 sq m (6,297 sq ft)
Permissible built-up area
918 sq m (9,886 sq ft)
Sanctioned built-up area
918 sq m (9,886 sq ft)
Address
Plot No 06 Gat No 150, Pimprala Shivar, Pimprala ShivarPIN 425001
Designated bank account
Hdfc Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
The Rudra Square is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Jun 2023

The latest completion date on record passed 3 years and 4 months ago.

Registered
8 May 2019
Promised
30 Jun 2023

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P499000207378 May 201930 Jun 2023—Sunil Ramnarayan MantriProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
The Rudra Square728

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

28 units registered

2BHK · 12 unitsShop · 16 units
TypeCarpet areaUnits
2BHK53.42 sq m · 575 sq ft8
2BHK57.13 sq m · 615 sq ft4
Shop9.76 sq m · 105 sq ft5
Shop11.09 sq m · 119 sq ft2
Shop11.45 sq m · 123 sq ft2
Shop12.36 sq m · 133 sq ft2
Shop14.79 sq m · 159 sq ft5

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00002
Open Space00002

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

The Rudra Square

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
  • Sanitary Fittings within the flats / premises75%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyWATER SUPPLY100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)SEPTIC TANK100%
  • Storm Water DrainsSTORM WATER DRAINS100%
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingRAIN WATER HARVESTING100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationELECTRICAL METER ROOM100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

19 documents held by Deedo, 23 filings listed on MahaRERA's project page

Allotment letter (2)

Title report

Encumbrance details

Form B

Commencement certificate (3)

Show all 42 documentsShow fewer documents

Form 2A (2)

Occupancy / completion certificate

  • Occupancy / completion certificate10 Oct 2020ViewSource

Form 4

Form 1

Form 2

Registration certificate

Other

Layout plan

Building plan (2)

Document library

  • Declaration in FORM BFORM B.pdf · uploaded 4 Mar 2019View
  • Building Plan Approval (IOD)BAP 1.pdf · uploaded 4 Mar 2019View
  • Details of encumbrancesNO ENCUMBARANCE CETIFICATE.pdf · uploaded 4 Mar 2019View
  • Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 4 Mar 2019View
  • Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 4 Mar 2019View
  • Proforma of Allotment letterANNEXURE A AFS.pdf · uploaded 4 Mar 2019View
  • Copy of the legal title reportLEGAL TITLE REPORT.pdf · uploaded 4 Mar 2019View
  • Commencement Certificates / NA Order for plotted developmentcommencemnt certificate(1).pdf · uploaded 26 Mar 2019View
  • Commencement Certificates / NA Order for plotted developmentExtention of Commencement.pdf · uploaded 26 Apr 2019View
  • Form 2ARFORM 2A .pdf · uploaded 13 Jul 2019View
  • Building Plan Approval (IOD)new building plan20 DEC 2019A.pdf · uploaded 18 Sep 2020View
  • Commencement Certificates / NA Order for plotted developmentcommencemnt certificate 12 DEC 19A.pdf · uploaded 18 Sep 2020View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentcompeletion certificarte dt 10 10 2020.pdf · uploaded 10 Oct 2020View
  • Architect’s Certificate on Completion of Project (Form 4)FORM 4 ARCHITECT CERTIFICATE.pdf · uploaded 13 Oct 2020View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 14 Oct 2020View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 14 Oct 2020View
  • Form 2AFORM 2A .pdf · uploaded 14 Oct 2020View

Promoter documents

  • Declaration Form BFORM B.pdf · uploaded 4 Mar 2019View
  • Legal Title reportLEGAL TITLE REPORT.pdf · uploaded 4 Mar 2019View

Technical documents

  • Building Plan ApprovalBAP 1.pdfView
  • Layout ApprovalLAYOUT.pdfView
  • Building Plan Approvalnew building plan20 DEC 2019A.pdfView

Proforma allotment letter

  • Proforma allotment letterANNEXURE A AFS.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Pimprala, Jalgaon taluka

Survey, CTS, gat or plot numbers

06150PLOT NO 06 GAT NO 150

As published on MahaRERA's project page

PLOT NO 06 GAT NO 150

Boundaries

North
Internal Colony Road
South
Gat No 152
East
Internal Colony Road
West
Gat No 151 2

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMilind Rathi—
ArchitectRahul Shah—
Chartered accountantDarshan Ramesh Jain—
EngineerMilind Rathi—

Source: MahaRERA project page. Contact details are not shown.