Ganesha Chaitanya

Completed

Pimprala, Jalgaon 425001 |Promoter: deepak prakash saraf

Residential / Group HousingRERAP49900025428
29 May 2020Registered with MahaRERA
9 Mar 2024Promised completion
1Building
15Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Unit types
2BHK15 units in all
Land area for this project
389 sq m (4,184 sq ft)
Permissible built-up area
100 sq m (1,076 sq ft)
Sanctioned built-up area
100 sq m (1,076 sq ft)
Address
gat no 64 plot no 7, vidyut colony, near gov.Engg collagePIN 425001
Designated bank account
The Jalgaon Peopels Cooperative Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Ganesha Chaitanya is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 9 Mar 2024

The latest completion date on record passed 2 years and 7 months ago.

Registered
29 May 2020
Promised
9 Mar 2024

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P4990002542829 May 20209 Mar 2024—deepak prakash sarafProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
ganesha chaitanya615

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

15 units registered

2BHK · 15 units
TypeCarpet areaUnits
2BHK44.62 sq m · 480 sq ft5
2BHK46.16 sq m · 497 sq ft5
2BHK48.58 sq m · 523 sq ft5

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered000014
Open Space00004

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

ganesha chaitanya

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyCOMPLETED100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)COMPLETED100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingCOMPLETED100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingCOMPLETED100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

15 documents held by Deedo, 19 filings listed on MahaRERA's project page

Title

Encumbrance

Commencement certificates

Form b

Registration certificate

Completion

Form 4

Form 2

Form 5

Other

Allotment letter

Layout plan

Building plans

Document library

  • Copy of the legal title reporttitle search report.pdf · uploaded 7 May 2020View
  • Details of encumbrancesencumbrance.pdf · uploaded 7 May 2020View
  • Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 7 May 2020View
  • Building Plan Approval / NA Order for plotted developmentApproved plan.pdf · uploaded 7 May 2020View
  • Commencement Certificates / NA Order for plotted developmentCommencement certificate.pdf · uploaded 7 May 2020View
  • Declaration in FORM Bform B Declaration.pdf · uploaded 7 May 2020View
  • Proforma of Allotment letterAgreement To Sell.pdf · uploaded 7 May 2020View
  • Commencement Certificates / NA Order for plotted developmentcommencement new.pdf · uploaded 30 Nov 2021View
  • Building Plan Approval / NA Order for plotted developmentplan chaitanya new.pdf · uploaded 30 Nov 2021View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentcompletion chaitanya.pdf · uploaded 11 May 2022View
  • Architect’s Certificate on Completion of Project (Form 4)chaitanya form4 architect.pdf · uploaded 11 May 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)form2 engg.pdf · uploaded 12 May 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)form 5 ganesha chaitanya.pdf · uploaded 17 May 2022View

Promoter documents

  • Legal Title reporttitle search report.pdf · uploaded 7 May 2020View
  • Declaration Form Bform B Declaration.pdf · uploaded 7 May 2020View

Technical documents

  • Layout ApprovalLayout.pdfView
  • Building Plan ApprovalApproved plan.pdfView
  • Building Plan Approvalplan chaitanya new.pdfView

Proforma allotment letter

  • Proforma allotment letterAgreement To Sell.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Pimprala, Jalgaon taluka

Survey, CTS, gat or plot numbers

647gat no 64 plot no 7

As published on MahaRERA's project page

gat no 64 plot no 7

Boundaries

North
plot no 8
South
road
East
plot no 4
West
road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPrashant m patil—
Chartered accountanttejas v kawadia—
Engineerdeepak prakash saraf—
Othersanjay natthu patil—

Source: MahaRERA project page. Contact details are not shown.