Skip to content
Deedo home
Menu

Krushnaji Arcade

Active

Pachora (Rural) (Ct), Jalgaon 424201 |Promoter: M/S. Shreyash Realties

15 Apr 2024Registered with MahaRERA
31 Jan 2028Promised completion
2Buildings
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Active
Buildings
2
Land area for this project
3,053 sq m (32,857 sq ft)
Permissible built-up area
12,389 sq m (1,33,356 sq ft)
Sanctioned built-up area
7,689 sq m (82,766 sq ft)
Planning authority
Nagar Parishad, Pachora
Address
Survey No 84/2+84/3, Bhadgaon Road, Sambhaji ChowkPIN 424201
Designated bank account
The Jalgaon Peopels Cooperative Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Krushnaji Arcade is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Jan 2028

Registered
15 Apr 2024
Promised
31 Jan 2028

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P4990005571515 Apr 202431 Jan 2028—M/S. Shreyash RealtiesProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Krushnaji Arcade8—
Store——

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered0000277
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Krushnaji Arcade

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
  • Sanitary Fittings within the flats / premises70%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Common areas and amenities

  • Internal Roads & Footpaths80%
  • Water Supply70%
  • Sewerage (Chamber, Lines, Septic Tank , STP)80%
  • Storm Water Drains80%
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage Water0%
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvesting0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirements20%
  • Electrical meter room, sub-station, receiving station20%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

58 documents held by Deedo, 104 filings listed on MahaRERA's project page

Commencement certificates

Others

Encumbrances

Allotment letters

Form 1s

Title

Form b

Registration certificate

Form 2s

Form 5

Form 2as

Layout plans

Document library

  • Copy of Layout Approval (in case of layout)1-1.pdf · uploaded 25 Jan 2024View
  • Copy of Layout Approval (in case of layout)1-9.pdf · uploaded 25 Jan 2024View
  • Copy of Layout Approval (in case of layout)2-9.pdf · uploaded 25 Jan 2024View
  • Copy of Layout Approval (in case of layout)3-9.pdf · uploaded 25 Jan 2024View
  • Copy of Layout Approval (in case of layout)4-9.pdf · uploaded 25 Jan 2024View
  • Copy of Layout Approval (in case of layout)5-9.pdf · uploaded 25 Jan 2024View
  • Copy of Layout Approval (in case of layout)6-9.pdf · uploaded 25 Jan 2024View
  • Copy of Layout Approval (in case of layout)7-9.pdf · uploaded 25 Jan 2024View
  • Copy of Layout Approval (in case of layout)8-9.pdf · uploaded 25 Jan 2024View
  • Copy of Layout Approval (in case of layout)9-9.pdf · uploaded 25 Jan 2024View
  • Building Plan Approval / NA Order for plotted development1-1.pdf · uploaded 25 Jan 2024View
  • Building Plan Approval / NA Order for plotted development1-9.pdf · uploaded 25 Jan 2024View
  • Building Plan Approval / NA Order for plotted development2-9.pdf · uploaded 25 Jan 2024View
  • Building Plan Approval / NA Order for plotted development3-9.pdf · uploaded 25 Jan 2024View
  • Building Plan Approval / NA Order for plotted development4-9.pdf · uploaded 25 Jan 2024View
  • Building Plan Approval / NA Order for plotted development5-9.pdf · uploaded 25 Jan 2024View
  • Building Plan Approval / NA Order for plotted development6-9.pdf · uploaded 25 Jan 2024View
  • Building Plan Approval / NA Order for plotted development7-9.pdf · uploaded 25 Jan 2024View
  • Building Plan Approval / NA Order for plotted development8-9.pdf · uploaded 25 Jan 2024View
  • Building Plan Approval / NA Order for plotted development9-9.pdf · uploaded 25 Jan 2024View
  • Commencement Certificates / NA Order for plotted developmentCOMM CERTIFICATE.pdf · uploaded 25 Jan 2024View
  • CERSAI detailsCERSAI_Search_Report_200294778245_For_Asset_Based_Search_26_01_2024_13_33_20_801.pdf · uploaded 26 Jan 2024View
  • a Details of encumbrances concerned to FinanceDECLARATION OF ENCUMBRANCES CONCERNED TO FINANCE.pdf · uploaded 29 Jan 2024View
  • b Details of encumbrances concerned to LegalDECLARATION OF ENCUMBRANCES CONCERNED TO FINANCE.pdf · uploaded 29 Jan 2024View
  • Deviation Report with respect to model copy of AgreementDeclaration Of No Deviation Agreement for sale.pdf · uploaded 29 Jan 2024View
  • a Details of encumbrances concerned to FinanceDeclaration of Encumbrances legal.pdf · uploaded 29 Jan 2024View
  • b Details of encumbrances concerned to LegalDeclaration of Encumbrances legal.pdf · uploaded 29 Jan 2024View
  • Deviation Report with respect to Allotment letterDecln allotment letter .pdf · uploaded 29 Jan 2024View
  • CERSAI detailsCERSAI report declaration.pdf · uploaded 30 Jan 2024View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSperate Form A Bank Details-.pdf · uploaded 30 Jan 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form - 2_Updated_KRUSHNAJI ARCADE.pdf · uploaded 30 Jan 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate -Form 1- -29-01-2024-.pdf · uploaded 30 Jan 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsDisclosure Of interest SANJAY H KUMAVAT.pdf · uploaded 5 Feb 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest (SAPNA KUMAVAT).pdf · uploaded 5 Feb 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest (KAVITA PATILl).pdf · uploaded 5 Feb 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest (KAMALBAI H KUMAVAT).pdf · uploaded 5 Feb 2024View
  • Proforma of Allotment letterAllottment Letter as per rera.pdf · uploaded 5 Feb 2024View
  • Proforma of Agreement for saleAgreement to sale Draft_Uploaded.pdf · uploaded 5 Feb 2024View
  • Other – LegalPartnership Deed_Uploaded.pdf · uploaded 5 Feb 2024View
  • Other – LegalPartnership Certificate.pdf · uploaded 5 Feb 2024View
  • Copy of the legal title reportlEGAL TITLE_11zon.pdf · uploaded 21 Feb 2024View
  • Other – Technical1 Annuxure A Delc cum Undertaking.pdf · uploaded 1 Mar 2024View
  • Declaration in FORM BForm B Final.pdf · uploaded 12 Mar 2024View
  • Declaration about Commencement Certificate5 Declaration About Commencement Certificate - Confirmation Final.pdf · uploaded 3 Apr 2024View
  • Declaration about Commencement CertificateFinal Appendix F Ack_merged.pdf · uploaded 3 Apr 2024View
  • Other – TechnicalFinal Appendix F Ack_merged.pdf · uploaded 3 Apr 2024View
  • Form 1Draft Form 1 - 30-06-2024 Draft done.pdf · uploaded 9 Oct 2025View
  • Form 2Form_-_2_June_24 (1).pdf · uploaded 9 Oct 2025View
  • Disclosure of Sold and Booked InventorySold Unsold jun 24.pdf · uploaded 9 Oct 2025View
  • Form 1Draft Form 1 - 30-09-2024 Draft done.pdf · uploaded 9 Oct 2025View
  • Form 2Form_-_2_Sept_24 (1).pdf · uploaded 9 Oct 2025View
  • Disclosure of Sold and Booked InventorySold Unsold Sept 24.pdf · uploaded 9 Oct 2025Source
  • Form 1Draft Form 1 - 31-12-2024 Draft done.pdf · uploaded 9 Oct 2025Source
  • Form 2Form_-_2_Dec_24 (1).pdf · uploaded 9 Oct 2025View
  • Disclosure of Sold and Booked InventorySold Unsold Dec 24.pdf · uploaded 9 Oct 2025View
  • Form 1Draft Form 1 - 31-03-2025 Draft done.pdf · uploaded 13 Oct 2025View
  • Form 2Form_-_2_March_25_KRUSHNAJI_ARCADE_.pdf · uploaded 13 Oct 2025View
  • Disclosure of Sold and Booked InventorySold Unsold March 25.pdf · uploaded 13 Oct 2025View
  • Form 5 (FY 2024-2025)SCANNED ANNEX F FORM 5.pdf · uploaded 25 Oct 2025View
  • Withdrawal Update Form 1Draft Form 1 - 30-06-2025 Draft done.pdf · uploaded 17 Dec 2025View
  • Withdrawal Update Form 2Form - 2_Updated_KRUSHNAJI ARCADE.pdf · uploaded 17 Dec 2025View
  • Withdrawal Update Form 1Draft Form 1 - 30-06-2025 Draft done.pdf · uploaded 17 Dec 2025View
  • Withdrawal Update Form 2Form - 2_Updated_KRUSHNAJI ARCADE.pdf · uploaded 17 Dec 2025View
  • Withdrawal Update Form 1Draft Form 1 - 30-06-2025 Draft done.pdf · uploaded 17 Dec 2025View
  • Withdrawal Update Form 2FORM 2 Jun 25.pdf · uploaded 17 Dec 2025Source
  • Withdrawal Update Form 1form 1_0001.pdf · uploaded 17 Dec 2025Source
  • Withdrawal Update Form 2Form 2 Sep 25.pdf · uploaded 17 Dec 2025View
  • Form 2A (FY 2024-2025)FORM 2A 2024-25- BHUSHAN PHATE SIR_0001.pdf · uploaded 6 Jan 2026View
  • Withdrawal Update Form 1Architects Certificate (Form 1) 31 12 2025 SIGN.pdf · uploaded 26 May 2026View
  • Withdrawal Update Form 2_Form_2_Dec_25__1_ SIGN.pdf · uploaded 26 May 2026View
  • Withdrawal Update Form 1Architects Certificate (Form 1) 31 12 2025 SIGN.pdf · uploaded 26 May 2026View
  • Withdrawal Update Form 2_Form_2_Dec_25__1_ SIGN.pdf · uploaded 26 May 2026View
  • Form 2A (FY 2025-2026)FORM-2A_Final V1.pdf · uploaded 25 Jul 2026View
  • Withdrawal Update Form 1Form-1_Jun 2026.pdf · uploaded 25 Jul 2026Source
  • Withdrawal Update Form 2Form 2 Jun 2026.pdf · uploaded 25 Jul 2026Source
  • Withdrawal Update Form 1Form-1_Jun 2026.pdf · uploaded 25 Jul 2026Source
  • Withdrawal Update Form 2Form 2 Jun 2026.pdf · uploaded 25 Jul 2026Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 7 Sep 2026View
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 7 Sep 2026View

Promoter documents

  • Legal Title reportlEGAL TITLE_11zon.pdf · uploaded 21 Feb 2024View
  • Declaration Form BForm B Final.pdf · uploaded 12 Mar 2024View

Technical documents

  • Layout Approval1-1.pdfView
  • Layout Approval1-9.pdfView
  • Layout Approval2-9.pdfView
  • Layout Approval3-9.pdfView
  • Layout Approval4-9.pdfView
  • Layout Approval5-9.pdfView
  • Layout Approval6-9.pdfView
  • Layout Approval7-9.pdfView
  • Layout Approval8-9.pdfView
  • Layout Approval9-9.pdfView
  • Building Plan Approval1-1.pdfView
  • Building Plan Approval1-9.pdfView
  • Building Plan Approval2-9.pdfView
  • Building Plan Approval3-9.pdfView
  • Building Plan Approval4-9.pdfView
  • Building Plan Approval5-9.pdfView
  • Building Plan Approval6-9.pdfView
  • Building Plan Approval7-9.pdfView
  • Building Plan Approval8-9.pdfView
  • Building Plan Approval9-9.pdfView

Other legal documents

  • Other – LegalPartnership Deed_Uploaded.pdfView
  • Other – LegalPartnership Certificate.pdfView

Proforma allotment letter

  • Proforma allotment letterAllottment Letter as per rera.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Pachora (Rural) (CT), Pachora taluka

Survey, CTS, gat or plot numbers

SURVEY NO 84/2+84/3

As published on MahaRERA's project page

SURVEY NO 84/2+84/3

Boundaries

North
S No 84-2 And 84-3
South
Bhadgaon Road
East
S No 84-4 -5
West
S No 84-1

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectThe Designers Collective Nashik—
Chartered accountantAnuj A Bafna—
Chartered accountantShashikant Dhamne—
EngineerBhushan Phate—
EngineerMr Milind Rathi—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology