Vasukamal Mithila

Completed

Jalgaon (M Corp.), Jalgaon 425001 |Promoter: Vasuakamal Five Elements

5 Sep 2019Registered with MahaRERA
12 Jul 2024Promised completion
231Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Completed
Unit types
1BHK, 2BHK, Residential Store, Shop, —231 units in all
Land area for this project
4,269 sq m (45,947 sq ft)
Permissible built-up area
10,753 sq m (1,15,744 sq ft)
Sanctioned built-up area
10,753 sq m (1,15,744 sq ft)
Address
CTS no 2699/A/2 to 6, Main Street, Shivaji NagarPIN 425001
Designated bank account
The Jalgaon Peopels Cooperative Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Vasukamal Mithila is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 12 Jul 2024

The latest completion date on record passed 2 years and 3 months ago.

Registered
5 Sep 2019
Promised
12 Jul 2024

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P499000222415 Sep 201912 Jul 2024—Vasuakamal Five ElementsProject page

Units and parking

231 units registered

1BHK · 98 units2BHK · 91 unitsResidential Store · 20 unitsShop · 21 units— · 1 unit
TypeCarpet areaUnits
1BHK29.77 sq m · 320 sq ft7
1BHK30.14 sq m · 324 sq ft7
1BHK30.4 sq m · 327 sq ft7
1BHK31.08 sq m · 335 sq ft7
1BHK31.75 sq m · 342 sq ft7
1BHK31.83 sq m · 343 sq ft7
1BHK31.89 sq m · 343 sq ft7
1BHK32.48 sq m · 350 sq ft7
1BHK35.26 sq m · 380 sq ft7
1BHK35.71 sq m · 384 sq ft7
1BHK35.77 sq m · 385 sq ft7
1BHK37.71 sq m · 406 sq ft7
1BHK38.75 sq m · 417 sq ft7
1BHK42.25 sq m · 455 sq ft7
2BHK44.09 sq m · 475 sq ft7
2BHK48.47 sq m · 522 sq ft7
2BHK49.82 sq m · 536 sq ft7
2BHK52.52 sq m · 565 sq ft7
2BHK54.53 sq m · 587 sq ft7
2BHK54.56 sq m · 587 sq ft7
2BHK55.57 sq m · 598 sq ft7
2BHK55.59 sq m · 598 sq ft7
2BHK56.98 sq m · 613 sq ft7
2BHK57.27 sq m · 616 sq ft7
2BHK57.75 sq m · 622 sq ft7
2BHK58.1 sq m · 625 sq ft7
2BHK59.85 sq m · 644 sq ft7
Residential Store10.4 sq m · 112 sq ft1
Residential Store11.04 sq m · 119 sq ft1
Residential Store11.05 sq m · 119 sq ft1
Residential Store12.05 sq m · 130 sq ft1
Residential Store12.88 sq m · 139 sq ft1
Residential Store13.1 sq m · 141 sq ft1
Residential Store13.1 sq m · 141 sq ft1
Residential Store13.17 sq m · 142 sq ft1
Residential Store13.82 sq m · 149 sq ft1
Residential Store13.99 sq m · 151 sq ft1
Residential Store14.01 sq m · 151 sq ft1
Residential Store14.95 sq m · 161 sq ft1
Residential Store15.02 sq m · 162 sq ft1
Residential Store15.05 sq m · 162 sq ft1
Residential Store15.21 sq m · 164 sq ft1
Residential Store15.4 sq m · 166 sq ft1
Residential Store15.47 sq m · 167 sq ft1
Residential Store16.43 sq m · 177 sq ft1
Residential Store33.72 sq m · 363 sq ft1
Residential Store83.92 sq m · 903 sq ft1
Shop10.4 sq m · 112 sq ft1
Shop11.24 sq m · 121 sq ft1
Shop11.25 sq m · 121 sq ft1
Shop13.17 sq m · 142 sq ft1
Shop13.28 sq m · 143 sq ft1
Shop13.36 sq m · 144 sq ft1
Shop13.38 sq m · 144 sq ft1
Shop13.6 sq m · 146 sq ft1
Shop13.61 sq m · 146 sq ft1
Shop13.91 sq m · 150 sq ft1
Shop14.05 sq m · 151 sq ft1
Shop14.09 sq m · 152 sq ft1
Shop14.09 sq m · 152 sq ft1
Shop14.3 sq m · 154 sq ft1
Shop14.3 sq m · 154 sq ft1
Shop14.58 sq m · 157 sq ft1
Shop15.45 sq m · 166 sq ft1
Shop15.75 sq m · 170 sq ft1
Shop16.07 sq m · 173 sq ft1
Shop16.42 sq m · 177 sq ft1
Shop17.58 sq m · 189 sq ft1
—13.1 sq m · 141 sq ft1

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered000055
Open Space00005

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Vasukamal Mithila

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyDone100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Done100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingDone100%
  • Street LightingNot applicable
  • Community BuildingsDone100%
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingDone100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsDone100%
  • Electrical meter room, sub-station, receiving stationDone100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingDone100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

20 documents held by Deedo, 33 filings listed on MahaRERA's project page

Encumbrance

Commencement certificates

Form b

Title

Registration certificate

Others

Form 5s

Form 1

Form 2

Form 2a

Layout plan

Building plan

Allotment letter

Document library

  • Details of encumbrancesDetails of Emcumbrances.pdf · uploaded 3 Aug 2019View
  • Commencement Certificates / NA Order for plotted developmentCommencemnt Certificate.pdf · uploaded 3 Aug 2019View
  • Declaration in FORM BForm B.pdf · uploaded 3 Aug 2019View
  • Building Plan Approval (IOD)Building Plan.pdf · uploaded 3 Aug 2019View
  • Proforma of Allotment letterAllotment Letter.pdf · uploaded 3 Aug 2019View
  • Copy of the legal title reportLegal Title Report.pdf · uploaded 28 Aug 2019View
  • OtherAgreement for Sale.pdf · uploaded 28 Aug 2019View
  • Copy of Layout Approval (in case of layout)Building Plan.pdf · uploaded 28 Aug 2019View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate 1.pdf · uploaded 12 Dec 2020View
  • Building Plan Approval (IOD)Building PLan 1.pdf · uploaded 12 Dec 2020View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5.pdf · uploaded 13 Jun 2021View
  • Disclosure of sold/ booked inventoryInventory List.pdf · uploaded 13 Jun 2021View
  • Status of Formation of Legal Entity (Society/Co Op etc.)Formation of Legal Entity.pdf · uploaded 4 Sep 2021Source
  • Status of ConveyanceConveyance Deed.pdf · uploaded 4 Sep 2021View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 7 Apr 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 7 Apr 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A.pdf · uploaded 7 Apr 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 5 Jul 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 5 Jul 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A.pdf · uploaded 5 Jul 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 (21-22).pdf · uploaded 1 Feb 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 (19-20).pdf · uploaded 1 Feb 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 (20-21).pdf · uploaded 1 Feb 2023View
  • Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 1 Feb 2023Source
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompletion Certificate.pdf · uploaded 1 Feb 2023Source
  • Architect’s Certificate on Completion of Project (Form 4)Form 4 - Architect Certificate.pdf · uploaded 12 Apr 2023Source

Promoter documents

  • Declaration Form BForm B.pdf · uploaded 3 Aug 2019View
  • Legal Title reportLegal Title Report.pdf · uploaded 28 Aug 2019View

Technical documents

  • Building Plan ApprovalBuilding Plan.pdfView
  • Layout ApprovalBuilding Plan.pdfView
  • Building Plan ApprovalBuilding PLan 1.pdfView

Other legal documents

  • OtherAgreement for Sale.pdfView

Proforma allotment letter

  • Proforma allotment letterAllotment Letter.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Jalgaon (M Corp.), Jalgaon taluka

Survey, CTS, gat or plot numbers

CTS no 2699/A/2 to 6

As published on MahaRERA's project page

CTS no 2699/A/2 to 6

Boundaries

North
24 MTR Road
South
Adj Railway Land
East
CTS 2699 A Plot no 7
West
CTS 2699 A Plot no 1

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMilind rathi—
Chartered accountantPratik Kejriwal—
EngineerMilind rathi—
OtherSarang Bhaviskar—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology