Skip to content
Deedo home
Menu

Ganesh Delight

Completed

Jalgaon (M Corp.), Jalgaon 425001 |Promoter: Gurudatta Global Developers

Residential / Group HousingRERAP49900013237
21 Sep 2017Registered with MahaRERA
20 Mar 2022Promised completion
1Building
20Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Unit types
1BHK, 2BHK20 units in all
Land area for this project
546 sq m (5,877 sq ft)
Permissible built-up area
841 sq m (9,048 sq ft)
Sanctioned built-up area
841 sq m (9,048 sq ft)
Address
gat no 101/3 plot no 43plus44PIN 425001
Designated bank account
The Jalgaon Peopels Cooperative Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.02690, 72.85538
Ganesh Delight is at latitude 19.02690, longitude 72.85538.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 20 Mar 2022

The latest completion date on record passed 4 years and 7 months ago.

Registered
21 Sep 2017
Promised
20 Mar 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P4990001323721 Sep 201720 Mar 2022—Gurudatta Global DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Ganesha Delight620

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

20 units registered

1BHK · 15 units2BHK · 5 units
TypeCarpet areaUnits
1BHK32.51 sq m · 350 sq ft5
1BHK33.31 sq m · 359 sq ft5
1BHK36.86 sq m · 397 sq ft5
2BHK50.88 sq m · 548 sq ft5

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space00006

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Ganesha Delight

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Internal Roads & FootpathsNot applicable
  • Internal Roads & FootpathsNot applicable
  • Internal Roads & FootpathsNot applicable
  • Water Supplyborewell & munciple corporation0%
  • Water Supplyborewell & munciple corporation100%
  • Water Supplyborewell & munciple corporation0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Sewerage0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Sewerage100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Sewerage100%
  • Storm Water DrainsNot applicable
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvesting100%
  • Water conservation /Rain water harvesting100%
  • Water conservation /Rain water harvesting0%
  • Energy managemcntNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open Parking60%
  • Open Parking6100%
  • Open Parking6100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

16 documents held by Deedo, 21 filings listed on MahaRERA's project page

Title

Encumbrance

Form b

Commencement certificate

Form 1

Form 2

Form 5s

Completion

Registration certificate

Form 4s

Other

Allotment letter

Layout plan

Building plan

Document library

  • Copy of the legal title reportScan Sep 7, 2017 (3).pdf · uploaded 12 Sep 2017View
  • Details of encumbrancesENCUMBRANCE.pdf · uploaded 12 Sep 2017View
  • Declaration in FORM BFORM B.pdf · uploaded 12 Sep 2017View
  • Proforma of Allotment letterAgreement To Sell BLANK RERA.pdf · uploaded 12 Sep 2017View
  • Building Plan Approval (IOD)plAN COPY.pdf · uploaded 12 Sep 2017View
  • Copy of Layout Approval (in case of layout)Scan Sep 12, 2017.pdf · uploaded 12 Sep 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engg.pdf · uploaded 18 Mar 2019View
  • Certificates of CA (Form 5)formno5.pdf · uploaded 18 Mar 2019View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)form1.pdf · uploaded 18 Mar 2019View
  • Commencement Certificates / NA Order for plotted developmentcommencement.pdf · uploaded 18 Mar 2019View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentdelight complition.pdf · uploaded 18 Mar 2021View
  • Certificates of CA (Form 5)delight CA form no 5.pdf · uploaded 18 Mar 2021View
  • Architect’s Certificate on Completion of Project (Form 4)GG.pdf · uploaded 22 Nov 2021View
  • Certificates of CA (Form 5)delight CA form no 5.pdf · uploaded 22 Nov 2021View
  • Architect’s Certificate on Completion of Project (Form 4)1 Architect’s Certificate on Completion of Project (Form 4).pdf · uploaded 8 Jan 2022View
  • Architect’s Certificate on Completion of Project (Form 4)form 4 delight.pdf · uploaded 2 Mar 2022View

Promoter documents

  • Legal Title reportScan Sep 7, 2017 (3).pdf · uploaded 12 Sep 2017View
  • Declaration Form BFORM B.pdf · uploaded 12 Sep 2017View

Technical documents

  • Building Plan ApprovalplAN COPY.pdfView
  • Layout ApprovalScan Sep 12, 2017.pdfView

Proforma allotment letter

  • Proforma allotment letterAgreement To Sell BLANK RERA.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Jalgaon (M Corp.), Jalgaon taluka

Survey, CTS, gat or plot numbers

101/3gat no 101/3 plot no 43plus44

As published on MahaRERA's project page

gat no 101/3 plot no 43plus44

Boundaries

North
Road
South
open space
East
plo no 45
West
road no 42

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVijay Madhukar Bhangale—
EngineerUjjwal Ravindra Chaudhari—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology