Skip to content

Sai Shri Sona Plaza

Completed

Jalgaon 425001 |Promoter: N & L Associates

12 Feb 2019Registered with MahaRERA
30 Jan 2023Promised completion
1Building
22Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Completed
Buildings
1
Unit types
FF FLAT No 01, FF FLAT No 02, FF FLAT No 03, FF FLAT No 04, GF SHOP No 01, GF SHOP No 02, GF SHOP No 03, GF SHOP No 04, Gf toilet, GS No 01, GS No 02, GS No 03, GS No 04, Residential store, SF FLAT No 01, SF FLAT No 02, SF FLAT No 03, SF FLAT No 04, TF FLAT No. 01, TF FLAT No. 02, TF FLAT No 03, TF FLAT No 0422 units in all
Land area for this project
319 sq m (3,429 sq ft)
Permissible built-up area
637 sq m (6,858 sq ft)
Sanctioned built-up area
637 sq m (6,858 sq ft)
Address
1697a/19/1, 1697a/19/2, Bhavani Peth, Near R C Bafna ShowroomPIN 425001
Designated bank account
Jalgaon Janata Sahakari Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Sai Shri Sona Plaza is at latitude 0.00000, longitude 0.00000.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Jan 2023

The latest completion date on record passed 3 years and 9 months ago.

Registered
12 Feb 2019
Promised
30 Jan 2023

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P4990001959812 Feb 201930 Jan 2023—N & L AssociatesProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Sai Shri Sona Plaza622

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

22 units registered

FF FLAT No 01 · 1 unitFF FLAT No 02 · 1 unitFF FLAT No 03 · 1 unitFF FLAT No 04 · 1 unitGF SHOP No 01 · 1 unitGF SHOP No 02 · 1 unitGF SHOP No 03 · 1 unitGF SHOP No 04 · 1 unitGf toilet · 1 unitGS No 01 · 1 unitGS No 02 · 1 unitGS No 03 · 1 unitGS No 04 · 1 unitResidential store · 1 unitSF FLAT No 01 · 1 unitSF FLAT No 02 · 1 unitSF FLAT No 03 · 1 unitSF FLAT No 04 · 1 unitTF FLAT No. 01 · 1 unitTF FLAT No. 02 · 1 unitTF FLAT No 03 · 1 unitTF FLAT No 04 · 1 unit
TypeCarpet areaUnits
FF FLAT No 0136.1 sq m · 389 sq ft1
FF FLAT No 0231.59 sq m · 340 sq ft1
FF FLAT No 0347.2 sq m · 508 sq ft1
FF FLAT No 0441.18 sq m · 443 sq ft1
GF SHOP No 0116.16 sq m · 174 sq ft1
GF SHOP No 0216.16 sq m · 174 sq ft1
GF SHOP No 0316.16 sq m · 174 sq ft1
GF SHOP No 0416.31 sq m · 176 sq ft1
Show all 22 unit rowsShow fewer unit rows
TypeCarpet areaUnits
Gf toilet4.39 sq m · 47 sq ft1
GS No 0110.38 sq m · 112 sq ft1
GS No 0210.38 sq m · 112 sq ft1
GS No 0310.38 sq m · 112 sq ft1
GS No 0410.47 sq m · 113 sq ft1
Residential store23.35 sq m · 251 sq ft1
SF FLAT No 0132.86 sq m · 354 sq ft1
SF FLAT No 0231.59 sq m · 340 sq ft1
SF FLAT No 0347.19 sq m · 508 sq ft1
SF FLAT No 0441.17 sq m · 443 sq ft1
TF FLAT No. 0121.97 sq m · 236 sq ft1
TF FLAT No. 0221.8 sq m · 235 sq ft1
TF FLAT No 0327.09 sq m · 292 sq ft1
TF FLAT No 0422.96 sq m · 247 sq ft1

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Sai Shri Sona Plaza

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyWATER SUPPLY100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)SEPTIC TANK90%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvesting100%
  • Energy managemcntMeter Room and Pump RoomNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationAC Equipment Area0%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

42 documents held by Deedo, 47 filings listed on MahaRERA's project page

Title report

Encumbrance details

Commencement certificate

Form B (2)

Allotment letter (2)

Form 1 (9)

Show all 89 documentsShow fewer documents

Form 1 (9)

Form 2 (8)

Form 2A (8)

Form 5

Occupancy / completion certificate (2)

  • Occupancy / completion certificate5 Feb 2020ViewSource
  • Occupancy / completion certificate17 Mar 2021ViewSource

Form 4

Registration certificate

Other (3)

Layout plan

Building plan

Document library

  • Copy of the legal title reportnew legal title.pdf · uploaded 18 Jan 2019View
  • Details of encumbrancesNO INCUMBERANCE CERTIFICATE.pdf · uploaded 25 Jan 2019View
  • Declaration in FORM BForm B Promoter.pdf · uploaded 25 Jan 2019View
  • Declaration in FORM BFORM B CO PROMOTER NL.pdf · uploaded 25 Jan 2019View
  • Commencement Certificates / NA Order for plotted developmentBP-2 COMMENCEMENT LETTER.PDF · uploaded 25 Jan 2019View
  • Building Plan Approval (IOD)NEW PLANT.pdf · uploaded 26 Jan 2019View
  • Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 26 Jan 2019View
  • Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 26 Jan 2019View
  • Proforma of Allotment letterANNEXURE A AFS.pdf · uploaded 29 Jan 2019View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)ACHITECH_CERTIFICATE_FORM_1.PDF · uploaded 10 Jun 2019View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER_CERTIFICATE_FORM_2.PDF · uploaded 10 Jun 2019View
  • Form 2AFORM_2_A.PDF · uploaded 11 Jul 2019View
  • Form 2AFORM_2A_ENG.PDF · uploaded 29 Jul 2019View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM_1_ARCH.PDF · uploaded 29 Jul 2019View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM_2_ENG.PDF · uploaded 29 Jul 2019View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)form_1_sai_sona.PDF · uploaded 7 Oct 2019View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form_2_sai_sona.PDF · uploaded 7 Oct 2019View
  • Form 2Aform_2A_sai_sona.PDF · uploaded 7 Oct 2019View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)NL_FORM_1_ARC.PDF · uploaded 5 Feb 2020View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM_2_SAI_SONA new.PDF · uploaded 5 Feb 2020View
  • Form 2ANL_FORM_2_A_ENG.PDF · uploaded 5 Feb 2020View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCOMPLITION_CERTIFICATE.PDF · uploaded 5 Feb 2020View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)CA CERTIFICATE ANNUAL FORM.pdf · uploaded 5 Feb 2020View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)form_1_arch_31032020_nla.pdf · uploaded 8 Jun 2020View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form_2_eng_3103202_nla.PDF · uploaded 8 Jun 2020Source
  • Form 2Aform_2_a_31032020_nla.PDF · uploaded 8 Jun 2020View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)nl_arc_form_1_30062020.PDF · uploaded 15 Jul 2020View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)nl_eng_form_2_30062020.PDF · uploaded 15 Jul 2020Source
  • Form 2Anl_form_2a_30062020.PDF · uploaded 15 Jul 2020View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM_1_ARCH_NLA3.PDF · uploaded 4 Nov 2020View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM_2_ENGG_NLA3.PDF · uploaded 4 Nov 2020View
  • Form 2AFORM_2_A_ENGG_NLA3.PDF · uploaded 4 Nov 2020View
  • Form 2AFORM_2_A_ENGG_NLA3.PDF · uploaded 4 Nov 2020View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)form_1_arch_3112_nla.PDF · uploaded 9 Mar 2021View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form_2_engg_3112_nla.PDF · uploaded 9 Mar 2021View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form_2_a_engg_3112_nla.PDF · uploaded 9 Mar 2021View
  • Architect’s Certificate on Completion of Project (Form 4)FORM_4_NLA.pdf · uploaded 17 Mar 2021View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentALL COMPLETION CERTIFICATE .pdf · uploaded 17 Mar 2021View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)FOM_1_SONA_NLA.PDF · uploaded 8 May 2021View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FOM_2_SONA_NLA.PDF · uploaded 8 May 2021View
  • Form 2AFOM_2A_SONA_NLA.PDF · uploaded 8 May 2021View

Promoter documents

  • Legal Title reportnew legal title.pdf · uploaded 18 Jan 2019View
  • Declaration Form BForm B Promoter.pdf · uploaded 25 Jan 2019View
  • Declaration Form BFORM B CO PROMOTER NL.pdf · uploaded 25 Jan 2019View

Technical documents

  • Building Plan ApprovalNEW PLANT.pdfView
  • Layout ApprovalLAYOUT.pdfView

Proforma allotment letter

  • Proforma allotment letterANNEXURE A AFS.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Jalgaon, Jalgaon taluka

Survey, CTS, gat or plot numbers

1697A/19/11697A/19/2

As published on MahaRERA's project page

1697A/19/1 , 1697A/19/2

Boundaries

North
4 Meter Road
South
CTS No 1697A 20
East
10 Meter Wide Road
West
Lane

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAnand Amol Mukund—
Chartered accountantDarshan Ramesh Jain—
EngineerHemant J Nyati—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology