Sahyadri Shikhar

Lapsed

Jalgaon 425001 |Promoter: Sahyadri Shikhar

20 Jul 2022Registered with MahaRERA
30 Sep 2024Promised completion
1Building
22Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Lapsed
Buildings
1
Unit types
2BHK, 3BHK, Shop22 units in all
Land area for this project
462 sq m (4,973 sq ft)
Permissible built-up area
1,655 sq m (17,817 sq ft)
Sanctioned built-up area
1,655 sq m (17,817 sq ft)
Address
Plot No 08, Gat No. -151/1, Plot No 08, Gat No. -151/1, At Pimprala Shivar, , JalgaonPIN 425001
Designated bank account
The Jalgaon Peopels Cooperative Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Sahyadri Shikhar is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Sep 2024

The latest completion date on record passed 2 years and 1 month ago.

Registered
20 Jul 2022
Promised
30 Sep 2024

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P4990004642720 Jul 202230 Sep 2024—Sahyadri ShikharProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Sahyadri Shikhar822

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

22 units registered

2BHK · 13 units3BHK · 7 unitsShop · 2 units
TypeCarpet areaUnits
2BHK40.35 sq m · 434 sq ft1
2BHK54.16 sq m · 583 sq ft6
2BHK54.32 sq m · 585 sq ft6
3BHK60.52 sq m · 651 sq ft6
3BHK84.88 sq m · 914 sq ft1
Shop30.51 sq m · 328 sq ft2

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Sahyadri Shikhar

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyWATER SUPPLY0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)SEPTIC TANK0%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationELECTRIC MATER ROOM0%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable
  • LIFTLIFT0%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

20 documents held by Deedo, 20 filings listed on MahaRERA's project page

Title

Form b

Commencement certificates

Others

Encumbrances

Allotment letters

Registration certificate

Layout plan

Building plan

Document library

  • Declaration in FORM BForm B.pdf · uploaded 21 Jun 2022View
  • Proforma of Allotment letterProforma_Allotment_Letter_compressed.pdf · uploaded 21 Jun 2022View
  • Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 21 Jun 2022View
  • Building Plan Approval / NA Order for plotted developmentBuilding plan.pdf · uploaded 21 Jun 2022View
  • Otherpartnership resolution.pdf · uploaded 21 Jun 2022View
  • Copy of the legal title reportlegal report.pdf · uploaded 21 Jun 2022View
  • Declaration about Commencement CertificateDeclaration Commencement certificate.pdf · uploaded 22 Jun 2022View
  • CERSAI detailsCERSAI_Search_Report_200240361837_For_Asset_Based_Search_22_06_2022_16_11_38_123.pdf · uploaded 22 Jun 2022View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameNo Encumbrsam Bank Certificate.pdf · uploaded 1 Jul 2022View
  • Deviation Report with respect to model copy of AgreementDeviation Report_Model Copy of Agreement.pdf · uploaded 1 Jul 2022View
  • a Details of encumbrances concerned to FinanceNew No Encumbrsam certificate.pdf · uploaded 1 Jul 2022View
  • b Details of encumbrances concerned to LegalNew No Encumbrsam certificate.pdf · uploaded 1 Jul 2022View
  • Deviation Report with respect to Allotment letterNo_Deviation_Allotment_Letter.pdf · uploaded 6 Jul 2022View
  • Commencement Certificates / NA Order for plotted developmentCommencement_Certificate-compressed.pdf · uploaded 10 Jul 2022View

Promoter documents

  • Declaration Form BForm B.pdf · uploaded 21 Jun 2022View
  • Legal Title reportlegal report.pdf · uploaded 21 Jun 2022View

Technical documents

  • Layout ApprovalLayout.pdfView
  • Building Plan ApprovalBuilding plan.pdfView

Other legal documents

  • Otherpartnership resolution.pdfView

Proforma allotment letter

  • Proforma allotment letterProforma_Allotment_Letter_compressed.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Jalgaon, Jalgaon taluka

Survey, CTS, gat or plot numbers

08GAT NO. 151/1PLOT NO 08

As published on MahaRERA's project page

PLOT NO 08, GAT NO. -151/1

Boundaries

North
Plot No 9
South
Plot No 7
East
Plot No 20
West
Plot No 7

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAnand A Mukund—
Chartered accountantCa Darshan Ramesh Jain—
EngineerAnand A Mukund—

Source: MahaRERA project page. Contact details are not shown.