Jk Pride · Jk Pride
Jalgaon · RERA P49900034265
IDBLD_0080127 floorsCompleted
7Sanctioned habitable floorsregistration certificate
31 Dec 2024Promised completion
Floors
7 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- Sanctioned habitable floors
- 7
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 56.3 m² (605 sq.ft) | 5 | not published |
| 2BHK | 56.8 m² (611 sq.ft) | 5 | not published |
| 3BHK | 82.3 m² (885 sq.ft) | 5 | not published |
| Office space | 14.1 m² (152 sq.ft) | 1 | not published |
| Office space | 45.1 m² (485 sq.ft) | 1 | not published |
| Shop | 32.2 m² (347 sq.ft) | 2 | not published |
| Total | 19 |
Parking
Spaces as declared on MahaRERA's project page.
| Type | Two-wheeler | Four-wheeler | Visitor | Total |
|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 0 |
| Open Space | 0 | 0 | 0 | 1 |
Construction progress
Work completed on this building, as the promoter reported it to MahaRERA (Form 1).
- Excavation0%
- Basement (if any)0%
- Podiums (if any)0%
- Plinth0%
- Stilt Floor0%
- Slabs of Super Structure0%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
- Sanitary Fittings within the flats / premises0%
Show all 11 activitiesShow fewer activities
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Data through9 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology