Skip to content
Deedo home
Menu

Aditya Gold City

Active

Jalgaon 425003 |Promoter: Aditya Builders And Developers

16 Dec 2019Registered with MahaRERA
30 Dec 2030Promised completion
3Buildings
2MahaRERA listings and orders

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Active
Buildings
3
Land area for this project
10,100 sq m (1,08,715 sq ft)
Permissible built-up area
18,599 sq m (2,00,196 sq ft)
Sanctioned built-up area
13,568 sq m (1,46,046 sq ft)
Recreational open space
1,972 sq m (21,231 sq ft)
Planning authority
Jalgaon Municipal Corporation
Address
SURVEY NO 38/2A/1 PLOT NO 1 TO 17, SURVEY NO 38/2A/1, Near Godawari Engineering College, National Highway No. 6, Besides Usha Motors, MIDC Area, Jalgaon - 425003, SHIVAR KHEDI BUDRUK, MIDC AREAPIN 425003
Designated bank account
Saraswat Cooperative Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 21.00344, 75.60343
Aditya Gold City is at latitude 21.00344, longitude 75.60343.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Dec 2030

Registered
16 Dec 2019
Promised
30 Dec 2030

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P4990002347816 Dec 201930 Dec 2030—Aditya Builders And DevelopersProject page

3 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Diamond14—
Pearl5—
Platinum9—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
DiamondClosed/Covered0000153
DiamondOpen Space00000
PearlClosed/Covered000025
PearlOpen Space00000
PlatinumClosed/Covered000076
PlatinumOpen Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Diamond

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises90%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.68%

Pearl

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Platinum

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsCEMENT ROADS AND PAVER BLOCKS50%
  • Water SupplyBOREWELL AND CONNECTION FROM CORPORATION25%
  • Sewerage (Chamber, Lines, Septic Tank , STP)UNDERGROUND CHAMBERS AND STP TO BE INSTALLED25%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingSHRUBS25%
  • Street LightingLED LIGHTS IN COMMON AREAS25%
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingRAIN WATER HARVESTING TO BE DONE25%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsFIRE FIGHTING SYSTEM TO BE INSTALLED25%
  • Electrical meter room, sub-station, receiving stationCOMMON METER ROOM AND DP TO BE INSTALLED10%
  • Aggregate area of recreational Open SpaceYET TO START0%
  • Open ParkingYET TO START25%
  • CHILDREN PLAY AREAYET TO START0%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

123 documents held by Deedo, 153 filings listed on MahaRERA's project page

Encumbrance

Commencement certificates

Title

Form 2as

Registration certificate

Others

Form 2s

Form 1s

Form 5s

Layout plan

Building plans

Allotment letter

Document library

  • Copy of the legal title reportAditya Gold City.pdf · uploaded 13 Oct 2019View
  • Details of encumbrancesgold city non encumbrance(2).pdf · uploaded 13 Oct 2019View
  • Copy of Layout Approval (in case of layout)LAY OUT.pdf · uploaded 13 Oct 2019View
  • Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 13 Oct 2019View
  • Building Plan Approval / NA Order for plotted developmentELEVATION DRAWING.pdf · uploaded 13 Oct 2019View
  • Building Plan Approval / NA Order for plotted developmentBLDG PLAN.pdf · uploaded 13 Oct 2019View
  • Declaration in FORM BAditya Gold City.pdf · uploaded 19 Oct 2019View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)MERGED FORM 1.pdf · uploaded 30 Nov 2019Source
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form_2_A_Gold_City.pdf · uploaded 30 Nov 2019View
  • Proforma of Allotment letterDraft AGREEMENT TO SALE_compressed.pdf · uploaded 30 Nov 2019Source
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 30 Nov 2019Source
  • OtherAGC ELEVATION.pdf · uploaded 30 Nov 2019View
  • OtherPEARL.pdf · uploaded 30 Nov 2019View
  • Proforma of Allotment letterproforma allotment letter.pdf · uploaded 10 Dec 2019View
  • Commencement Certificates / NA Order for plotted developmentcommencement upper floor diamond bldg.pdf · uploaded 19 Mar 2024View
  • Building Plan Approval / NA Order for plotted developmentSCAN 22-06-2022_compressed.pdf · uploaded 19 Mar 2024View
  • Building Plan Approval / NA Order for plotted developmentsanction plan upper floor.pdf · uploaded 19 Mar 2024View
  • Status of Formation of Legal Entity (Society/Co Op etc.)आदित्य गोल्ड सिटी चुक दुरुस्ती घोषणा पत्र 2_compressed-1-15.pdf · uploaded 19 Mar 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Q3FY1920.pdf · uploaded 10 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Q4FY1920.pdf · uploaded 10 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Q1FY2021.pdf · uploaded 10 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Q2FY2021.pdf · uploaded 10 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Q3FY2021.pdf · uploaded 10 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Q4FY2021.pdf · uploaded 10 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Q1FY2122.pdf · uploaded 10 Apr 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Q2FY2122.pdf · uploaded 10 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Q2FY2122.pdf · uploaded 10 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Q3FY2122.pdf · uploaded 10 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Q4FY2122.pdf · uploaded 10 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Q1FY2223.pdf · uploaded 10 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Q2FY2223.pdf · uploaded 10 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Q3FY2223.pdf · uploaded 10 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Q4FY2223.pdf · uploaded 10 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)FinalForm2FY2021uploaded.pdf · uploaded 11 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)FinalForm2FY2122uploaded.pdf · uploaded 11 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)FinalForm2FY2223uploaded.pdf · uploaded 11 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Q1FY2324.pdf · uploaded 11 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Q2FY2324.pdf · uploaded 11 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Q3FY2324.pdf · uploaded 11 Apr 2024View
  • Commencement Certificates / NA Order for plotted developmentcomletter.pdf · uploaded 18 Jan 2025View
  • Building Plan Approval / NA Order for plotted developmentsheet01.pdf · uploaded 18 Jan 2025View
  • Building Plan Approval / NA Order for plotted developmentsheet02.pdf · uploaded 18 Jan 2025View
  • Building Plan Approval / NA Order for plotted developmentSheet03.pdf · uploaded 18 Jan 2025View
  • Building Plan Approval / NA Order for plotted developmentsheet04.pdf · uploaded 18 Jan 2025View
  • Building Plan Approval / NA Order for plotted developmentsheet06.pdf · uploaded 18 Jan 2025View
  • Building Plan Approval / NA Order for plotted developmentsheet07.pdf · uploaded 18 Jan 2025View
  • Form 1Form131122019.pdf · uploaded 4 Mar 2026View
  • Form 2Form231122019.pdf · uploaded 4 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI31122019.pdf · uploaded 4 Mar 2026View
  • Form 1Form131122019.pdf · uploaded 4 Mar 2026View
  • Form 2Form231122019.pdf · uploaded 4 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI31122019.pdf · uploaded 4 Mar 2026View
  • Form 1Form130062020.pdf · uploaded 4 Mar 2026View
  • Form 2Form230062020.pdf · uploaded 4 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI30062020.pdf · uploaded 4 Mar 2026Source
  • Form 1Form130092020.pdf · uploaded 4 Mar 2026Source
  • Form 2Form230092020.pdf · uploaded 4 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI30092020.pdf · uploaded 4 Mar 2026View
  • Form 1Form131122020.pdf · uploaded 4 Mar 2026View
  • Form 2Form231122020.pdf · uploaded 4 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI31122020.pdf · uploaded 4 Mar 2026View
  • Form 1Form131032021.pdf · uploaded 4 Mar 2026View
  • Form 2Form231032021.pdf · uploaded 4 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI31032021.pdf · uploaded 4 Mar 2026View
  • Form 1Form130062021.pdf · uploaded 4 Mar 2026View
  • Form 2Form230062021.pdf · uploaded 4 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI30062021.pdf · uploaded 4 Mar 2026View
  • Form 1Form130092021.pdf · uploaded 4 Mar 2026View
  • Form 2Form230092021.pdf · uploaded 4 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI30092021.pdf · uploaded 4 Mar 2026View
  • Form 1Form131122021.pdf · uploaded 4 Mar 2026View
  • Form 2Form231122021.pdf · uploaded 4 Mar 2026Source
  • Disclosure of Sold and Booked InventoryUI31122021.pdf · uploaded 4 Mar 2026Source
  • Form 1Form131032022.pdf · uploaded 4 Mar 2026View
  • Form 2Form231032022.pdf · uploaded 4 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI31032022.pdf · uploaded 4 Mar 2026View
  • Form 1Form130062022.pdf · uploaded 5 Mar 2026View
  • Form 2Form230062022.pdf · uploaded 5 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI30062022.pdf · uploaded 5 Mar 2026View
  • Form 1Form130092022.pdf · uploaded 5 Mar 2026View
  • Form 2Form230092022.pdf · uploaded 5 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI30092022.pdf · uploaded 5 Mar 2026View
  • Form 1Form131122022.pdf · uploaded 5 Mar 2026View
  • Form 2Form231122022.pdf · uploaded 5 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI31122022.pdf · uploaded 5 Mar 2026View
  • Form 1Form131032023.pdf · uploaded 5 Mar 2026View
  • Form 2Form231032023.pdf · uploaded 5 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI31032023.pdf · uploaded 5 Mar 2026View
  • Form 1Form130062023.pdf · uploaded 5 Mar 2026View
  • Form 2Form230062023.pdf · uploaded 5 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI30062023.pdf · uploaded 5 Mar 2026View
  • Form 1Form130092023.pdf · uploaded 5 Mar 2026View
  • Form 2Form230092023.pdf · uploaded 5 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI30092023.pdf · uploaded 5 Mar 2026View
  • Form 1Form131122023.pdf · uploaded 5 Mar 2026View
  • Form 2Form231122023.pdf · uploaded 5 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI31122023.pdf · uploaded 5 Mar 2026View
  • Form 1Form131032024.pdf · uploaded 5 Mar 2026View
  • Form 2Form231032024.pdf · uploaded 5 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI31032024.pdf · uploaded 5 Mar 2026View
  • Form 1Form130062024.pdf · uploaded 5 Mar 2026View
  • Form 2Form230062024.pdf · uploaded 5 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI30062024.pdf · uploaded 5 Mar 2026View
  • Form 1Form130092024.pdf · uploaded 5 Mar 2026View
  • Form 2Form230092024.pdf · uploaded 5 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI30092024.pdf · uploaded 5 Mar 2026View
  • Form 1Form131122024.pdf · uploaded 5 Mar 2026View
  • Form 2Form231122024.pdf · uploaded 5 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI31122024.pdf · uploaded 5 Mar 2026Source
  • Form 1Form131032025.pdf · uploaded 5 Mar 2026Source
  • Form 2Form231032025.pdf · uploaded 5 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI31032025.pdf · uploaded 5 Mar 2026View
  • Form 1Form130062025.pdf · uploaded 5 Mar 2026View
  • Form 2Form230062025.pdf · uploaded 5 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI30062025.pdf · uploaded 5 Mar 2026View
  • Form 1Form130092025.pdf · uploaded 5 Mar 2026View
  • Form 2Form230092025.pdf · uploaded 5 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI30092025.pdf · uploaded 5 Mar 2026View
  • Form 1Form131122025Final.pdf · uploaded 5 Mar 2026View
  • Form 2Form231122025.pdf · uploaded 5 Mar 2026View
  • Disclosure of Sold and Booked InventoryUI31122025.pdf · uploaded 5 Mar 2026View
  • Form 5 (FY 2019-2020)AGC - Form 5_2020.pdf · uploaded 22 Mar 2026View
  • Form 5 (FY 2020-2021)AGC - Form 5_2021.pdf · uploaded 22 Mar 2026View
  • Form 5 (FY 2021-2022)AGC - Form 5_2022.pdf · uploaded 22 Mar 2026View
  • Form 5 (FY 2022-2023)AGC - Form 5_2023.pdf · uploaded 22 Mar 2026View
  • Form 5 (FY 2023-2024)AGC - Form 5_2024.pdf · uploaded 22 Mar 2026View
  • Form 5 (FY 2024-2025)AGC - Form 5_2025.pdf · uploaded 22 Mar 2026View
  • Form 2A (FY 2019-2020)Form2A31032020.pdf · uploaded 30 Mar 2026View
  • Form 2A (FY 2020-2021)Form2A31032021.pdf · uploaded 30 Mar 2026View
  • Form 2A (FY 2021-2022)3Form2A31032022.pdf · uploaded 31 Mar 2026View
  • Form 2A (FY 2022-2023)4Form2A31032023.pdf · uploaded 31 Mar 2026View
  • Form 2A (FY 2023-2024)5Form2A31032024.pdf · uploaded 31 Mar 2026View
  • Form 2A (FY 2024-2025)6Form2A31032025.pdf · uploaded 31 Mar 2026View
  • Form 2A (FY 2025-2026)7Form2A31032026.pdf · uploaded 31 Mar 2026View
  • Form 1Form131032026.pdf · uploaded 21 May 2026View
  • Form 2Form231032026.pdf · uploaded 21 May 2026View
  • Disclosure of Sold and Booked InventoryUI31032026.pdf · uploaded 21 May 2026View

Promoter documents

  • Legal Title reportAditya Gold City.pdf · uploaded 13 Oct 2019View
  • Declaration Form BAditya Gold City.pdf · uploaded 19 Oct 2019View

Technical documents

  • Layout ApprovalLAY OUT.pdfView
  • Building Plan ApprovalELEVATION DRAWING.pdfView
  • Building Plan ApprovalBLDG PLAN.pdfView
  • Building Plan ApprovalSCAN 22-06-2022_compressed.pdfView
  • Building Plan Approvalsanction plan upper floor.pdfView
  • Building Plan Approvalsheet01.pdfView
  • Building Plan Approvalsheet02.pdfView
  • Building Plan ApprovalSheet03.pdfView
  • Building Plan Approvalsheet04.pdfView
  • Building Plan Approvalsheet06.pdfView
  • Building Plan Approvalsheet07.pdfView

Other legal documents

  • OtherAGC ELEVATION.pdfView
  • OtherPEARL.pdfView

Proforma allotment letter

  • Proforma allotment letterproforma allotment letter.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Jalgaon, Jalgaon taluka

Survey, CTS, gat or plot numbers

38/2A/1SURVEY NO 38/2A/1 PLOT NO 1 TO 17

As published on MahaRERA's project page

SURVEY NO 38/2A/1 PLOT NO 1 TO 17

Boundaries

North
Service Road And National Highway No 6
South
18 Meter Wide Road
East
Survey No 38-2b-A
West
Survey No 38-1

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMayuresh Agrawal—
ArchitectMilind Rathi—
Chartered accountantNachiket Jakhetiya—
Chartered accountantRavindra Chhajer—
EngineerMilind Rathi—
OtherShakil She Shamil Pinjari—
OtherShrikant Sarolkar—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · MahaRERA regulatory lists and ordersData through is when MahaRERA's project page was last read.Methodology