1 · Shri Gajanan Complex
Bhadgaon · RERA P49900048149
4Sanctioned habitable floorsregistration certificate
31 Dec 2025Promised completion
Floors
4 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- Sanctioned habitable floors
- 4
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 5.4 m² (58 sq.ft) | 18 | not published |
| Shop | 5.5 m² (59 sq.ft) | 3 | not published |
| Shop | 5.6 m² (60 sq.ft) | 2 | not published |
| Shop | 5.7 m² (61 sq.ft) | 3 | not published |
| Shop | 6 m² (65 sq.ft) | 3 | not published |
| Shop | 6.1 m² (66 sq.ft) | 3 | not published |
| Shop | 6.4 m² (68 sq.ft) | 3 | not published |
| Shop | 6.7 m² (72 sq.ft) | 3 | not published |
| Shop | 7 m² (76 sq.ft) | 3 | not published |
| Shop | 90.1 m² (970 sq.ft) | 1 | not published |
| Total | 42 |
Parking
Spaces as declared on MahaRERA's project page.
| Type | Two-wheeler | Four-wheeler | Visitor | Total |
|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 0 |
| Open Space | 0 | 0 | 0 | 15 |
Construction progress
Work completed on this building, as the promoter reported it to MahaRERA (Form 1).
- Excavation100%
- Basement (if any)50%
- Podiums (if any)50%
- Plinth50%
- Stilt Floor0%
- Slabs of Super Structure0%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
- Sanitary Fittings within the flats / premises0%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%