Rajaram Bapu Mega City Phase I

Lapsed

Bhadgaon, Jalgaon 424105 |Promoter: Kishor Pitambar Patil

Residential / Group HousingRERAP49900015754
22 Mar 2018Registered with MahaRERA
30 Mar 2023Promised completion
2Buildings
20Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Lapsed
Buildings
2
Unit types
1 BHK, 2 BHK20 units in all
Land area for this project
1,094 sq m (11,774 sq ft)
Permissible built-up area
981 sq m (10,557 sq ft)
Sanctioned built-up area
981 sq m (10,557 sq ft)
Address
46, 47, 48, 49, 50, 51, 52, 53, 54, 107, 108, 109, 110, 111, 112, 113, 114 Of Gat No 604, Parola Road, PethPIN 424105
Designated bank account
Hdfc Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.97509, 73.05233
Rajaram Bapu Mega City Phase I is at latitude 18.97509, longitude 73.05233.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Mar 2023

The latest completion date on record passed 3 years and 7 months ago.

Registered
22 Mar 2018
Promised
30 Mar 2023

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P4990001575422 Mar 201830 Mar 2023—Kishor Pitambar PatilProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Wing A211
Wing C29

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

20 units registered

1 BHK · 19 units2 BHK · 1 unit
BuildingTypeCarpet areaUnits
Wing A1 BHK50.66 sq m · 545 sq ft3
Wing A1 BHK51.14 sq m · 550 sq ft7
Wing A2 BHK60.64 sq m · 653 sq ft1
Wing C1 BHK32.82 sq m · 353 sq ft7
Wing C1 BHK50.66 sq m · 545 sq ft2

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Wing AClosed/Covered00000
Wing AOpen Space00000
Wing CClosed/Covered00000
Wing COpen Space00001

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Wing A

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Wing C

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsCompleted100%
  • Internal Roads & FootpathsCompleted100%
  • Water SupplyCompleted100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Completed100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingCompleted100%
Show all 16 activitiesShow fewer activities
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

10 documents held by Deedo, 13 filings listed on MahaRERA's project page

Encumbrance details

Title report

Commencement certificate

Form B

Registration certificate

Occupancy / completion certificate

  • Occupancy / completion certificate23 Jan 2023ViewSource

Other

Layout plan

Show all 23 documentsShow fewer documents

Building plan

Allotment letter

Document library

  • Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 6 Mar 2018View
  • Details of encumbrancesEncumbarance Certificate.pdf · uploaded 6 Mar 2018View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate of Rajarambapu Mega City Phase I.pdf · uploaded 15 Mar 2018View
  • Building Plan Approval (IOD)Building Plan Approval.pdf · uploaded 15 Mar 2018View
  • Copy of the legal title reportRBMC Search Report.pdf · uploaded 15 Mar 2018View
  • Declaration in FORM BForm B Affidavit.pdf · uploaded 15 Mar 2018View
  • Proforma of Allotment letterDraft Agreement to Sale.pdf · uploaded 15 Mar 2018View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentRBMC PH 1 Occupancy Cert.pdf · uploaded 23 Jan 2023View

Promoter documents

  • Legal Title reportRBMC Search Report.pdf · uploaded 15 Mar 2018View
  • Declaration Form BForm B Affidavit.pdf · uploaded 15 Mar 2018View

Technical documents

  • Building Plan ApprovalBuilding Plan Approval.pdfView
  • Layout ApprovalLayout.pdfView

Proforma allotment letter

  • Proforma allotment letterDraft Agreement to Sale.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Bhadgaon, Bhadgaon taluka

Survey, CTS, gat or plot numbers

107108109110111112113114 OF GAT NO 604464748495051525354604

As published on MahaRERA's project page

46,47,48,49,50,51,52,53,54,107,108,109,110,111,112,113,114 OF GAT NO 604

Boundaries

North
12 Mtr Road
South
9 Mtr Road
East
Gat No 314
West
Open Space And Plot No 45 Of Gat No 604

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectBhagyashri Patel—
OtherRavindra Bhramhane—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology