Vtp Corporation Llp

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Urban RiseP52100000278Pisoli2017Certificate Signed31 Dec 201730 Jun 2018+6 months
Purvanchal Phase2 C D EP52100009865Kesnand2017Certificate Signed31 Dec 202331 Dec 2023On date
The HubP52100033109Kesnand2022Certificate Signed31 Dec 202330 Jun 2025+18 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Urban Rise+6 mo
  • Purvanchal Phase2 C D EOn date
  • The Hub+18 mo

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 18 months, for The Hub (P52100033109).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology