Vilas Javdekar Lifestyle Developers Pvt. Ltd

Company or firm · 6 projects · 6 MahaRERA registrations

Also appears as Vilas Javdekar Lifestyle Developers Pvt. Ltd.

6Projects6 RERA registrations
0Completedas reported on MahaRERA project pages
80%Kept RERA date4 of 5 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
PortiaP52100000301Baner2017Certificate Signed31 Dec 201831 Dec 2019+12 months
Yashwin EncoreP52100017756Wakad2018Certificate Signed30 Dec 202430 Dec 2024On date
MHADA - Yashwin EncoreP52100020924Wakad2019Certificate Signed30 Dec 202430 Dec 2024On date
Yashwin NuovoCentroP52100034523Wakad2022Certificate Signed30 Jun 202630 Jun 2026On date
172W Inclusive HousingP52100049412Wakad2023Certificate Signed30 Jun 202630 Jun 2026On date
VJ IndiLife WakadP52100050594Wakad2023Certificate Signed30 Jun 202730 Jun 2027On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Portia+12 mo
  • Yashwin EncoreOn date
  • MHADA - Yashwin EncoreOn date
  • Yashwin NuovoCentroOn date
  • 172W Inclusive HousingOn date
  • VJ IndiLife WakadOn date

Track record notes

  • 4 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Portia (P52100000301).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology