Company or firm · first RERA registration 2018

Vedant Developers

Of 2 registrations whose promised date has arrived, 1 were never extended past it (50%).

Projects22 RERA registrations
Kept RERA date50%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record

1 registration of 2 moved past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Parvati PrideP52900016208Banda (Ct)Not on record28 May 202128 Nov 2024+42 mo
Ambayani ChslP51700048169Badlapur (M Cl)Not on record29 Jun 2025—On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology