Truewin Realty Limited

Company or firm · 2 projects · 9 MahaRERA registrations

2Projects9 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date9 of 9 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
8Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Ashok Nirvaan Villa 43P52100009630Lonavala (M Cl)2017Certificate Signed31 Mar 201831 Mar 2018On date
Ashok NirvaanP52100026350Lonavala (M Cl)2020Certificate Signed4 Aug 20244 Aug 2024On date
Ashok NirvaanP52100026371Lonavala (M Cl)2020Certificate Signed4 Aug 20244 Aug 2024On date
Ashok NirvaanP52100026374Lonavala (M Cl)2020Certificate Signed4 Aug 20244 Aug 2024On date
Ashok NirvaanP52100026375Lonavala (M Cl)2020Certificate Signed4 Aug 20244 Aug 2024On date
Ashok NirvaanP52100026377Lonavala (M Cl)2020Certificate Signed4 Aug 20244 Aug 2024On date
Ashok NirvaanP52100026382Lonavala (M Cl)2020Certificate Signed4 Aug 20244 Aug 2024On date
Ashok NirvaanP52100026418Lonavala (M Cl)2020Certificate Signed4 Aug 20244 Aug 2024On date
Ashok NirvaanP52100026442Lonavala (M Cl)2020Certificate Signed4 Aug 20244 Aug 2024On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Ashok Nirvaan Villa 43On date
  • Ashok NirvaanOn date
  • Ashok NirvaanOn date
  • Ashok NirvaanOn date
  • Ashok NirvaanOn date
  • Ashok NirvaanOn date
  • Ashok NirvaanOn date
  • Ashok NirvaanOn date
  • Ashok NirvaanOn date

Track record notes

  • 9 of 9 registrations whose RERA proposed completion date has passed were never extended beyond it.

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology