Tata Housing Development Company Limited

Company or firm · 2 projects · 3 MahaRERA registrations

2Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
2Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Amantra Phase 2P51700000308Ranjnoli2017Certificate Signed31 Mar 201831 Mar 2018On date
AvezaP51900007527Kurla2017Certificate Signed30 Dec 202329 Dec 2024+12 months
AvezaP51900007740Kurla2017Certificate Signed30 Dec 202530 Dec 2025On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Amantra Phase 2On date
  • Aveza+12 mo
  • AvezaOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Aveza (P51900007527).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology