Tata Housing Development Company Limited
Company or firm · 2 projects · 3 MahaRERA registrations
2Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
2Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Amantra Phase 2P51700000308 | Ranjnoli | 2017 | Certificate Signed | 31 Mar 2018 | 31 Mar 2018 | On date |
| AvezaP51900007527 | Kurla | 2017 | Certificate Signed | 30 Dec 2023 | 29 Dec 2024 | +12 months |
| AvezaP51900007740 | Kurla | 2017 | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Aveza (P51900007527).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: AVEZA PHASE 1 (Regulatory Case No. 448 OF 2025) dated 07 Sept, 2026. · Aveza · P51900007527 · 7 Sep 2026
- Regulatory orderRegulatory order: PROJECT NAME: AVEZA PHASE 1 (Regulatory Case No. 448 OF 2025) dated 07 Sept, 2026. · Aveza · P51900007740 · 7 Sep 2026 · the order may refer to a related project
- DeregisteredDeregistered: Aveza Phase 2 · Aveza · P51900007740
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology