Tara Constructions
Company or firm · 3 projects · 3 MahaRERA registrations
Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 3 past their proposed date, not extended
Median delay+18 movs RERA proposed date · 3 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| WestbrookP52100003178 | Ambegaon Bk | 2017 | Not reported | 30 Sep 2020 | 31 May 2024 | +44 months |
| 55 SukhniwasP52100003717 | Pune (M Corp.) | 2017 | Not reported | 30 Jun 2019 | 29 Dec 2020 | +18 months |
| Westbrook AvenueP52100046193 | Ambegaon Bk | 2022 | Not reported | 30 Jun 2023 | 29 Jun 2024 | +12 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 44 months, for Westbrook (P52100003178).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology