Snehanjali And S.B.Developers Pvt.Ltd
Company or firm · 1 project · 1 MahaRERA registration
Also appears as Snehanjali And S.B.Developers Pvt.Ltd.
1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+45 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| O2P51800008513 | Kurla | 2017 | Certificate Signed | 30 Jun 2022 | 4 Mar 2026 | +45 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 45 months, for O2 (P51800008513).
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
- Listed as an NCLT insolvency projectListed as NCLT project: O2 · O2 · P51800008513
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology