Skyspace Builtek

Company or firm · 1 project · 2 MahaRERA registrations

1Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+9 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Raj SilverstoneP51700029081Badlapur (M Cl)2021Certificate Signed31 Dec 202230 Jun 2023+6 months
Raj SilverstoneP51700047261Badlapur (M Cl)2022Certificate Signed31 Jul 202531 Jul 2026+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Raj Silverstone+6 mo
  • Raj Silverstone+12 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Raj Silverstone (P51700047261).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology