None of 2 registrations has reached its promised completion date yet.

Projects22 RERA registrations
Kept RERA dateNone due yet
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record

1 registration of 2 moved past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Shubh SerenityP52100053397Pune (M Corp.)Not on record30 Jun 2027—On date
Shubh Swarovski Wing AP52100055505WakadCertificate Signed12 Oct 202812 Feb 2029+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology