Shriya Builders & Land Developers
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+39 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| ShantkamalP99000007369 | Vasaivirar City (M Corp) | 2017 | Not reported | 30 Sep 2022 | 31 Dec 2025 | +39 months |
| Moreshwar NiwasP99000012305 | Vasaivirar City (M Corp) | 2017 | Not reported | 30 Mar 2021 | 31 Dec 2025 | +57 months |
| Manjerekar KrupaP99000028387 | Vasaivirar City (M Corp) | 2021 | Not reported | 15 Feb 2024 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 57 months, for Moreshwar Niwas (P99000012305).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology