Shree Tirupati Greenfield Developers
Company or firm · 2 projects · 2 MahaRERA registrations
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 2 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Marigold B wingP51700004654 | Thane (M Corp.) | 2017 | Certificate Signed | 30 Jun 2028 | 30 Oct 2028 | +4 months |
| DaffodilP51700005442 | Thane (M Corp.) | 2017 | Certificate Signed | 30 Dec 2026 | 30 Apr 2027 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- Longest extension on record: 4 months, for Marigold B wing (P51700004654).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME:MARIGOLD B WING (Regulatory Case No. 243 OF 2024) dated 21 June 2024. · Marigold B wing · P51700004654 · 21 Jun 2024
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology