Company or firm · first RERA registration 2017
Shilpa Developers
Of 2 registrations whose promised date has arrived, 0 were never extended past it (0%).
Projects22 RERA registrations
Kept RERA date0%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
2 registrations of 2 moved past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Heramb VillaP99000010104 | Palghar | Certificate Signed | 31 Dec 2019 | 31 Mar 2023 | +39 mo |
| Shilpa Mansi DarshanP99000019969 | Palghar | Certificate Signed | 30 Jun 2021 | 31 Dec 2023 | +30 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology