Skip to content

Sara Infrastructures

Company or firm · 8 projects · 10 MahaRERA registrations · 1 reported completed

8Projects10 RERA registrations
1Completedas reported on MahaRERA project pages
75%Kept RERA date6 of 8 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sara Swapnangan - A4, A5, A6 BuildingsP51500001363Gangapur Jahagir2017Completed31 Dec 2018—On date
Sara MetrovilleP52100001689Punawale2017Certificate Signed30 Sep 201930 Sep 2019On date
Sara MetrovilleP52100002174Punawale2017Certificate Signed30 Jun 202130 Jun 2022+12 months
Sara MetrovilleP52100004198Punawale2017Certificate Signed30 Dec 202130 Dec 2021On date
Sara Swapnangan - Row HousesP51500001944Gangapur Jahagir2017Certificate Signed31 Dec 201731 Dec 2017On date
Sara Swapnangan Phase-2, H-1, H-2 And G Type Row HouseP51500019536Gangapur Jahagir2019Certificate Signed30 Oct 202130 Oct 2021On date
Sara Angan B2, B3, C1 And C2 Type BuildingP51500032885Gangapur Jahagir2022Certificate Signed31 Mar 202331 Dec 2026+45 months
Sara Angan Phase-1 A1 -B1 Type BuildingP51500049187Gangapur Jahagir2023Certificate Signed31 Dec 202531 Dec 2025On date
Sara Swarajya Phase-IP51500077523Wadgaon Kolhati (Ct)2024Active31 Dec 2030—On date
Sara NiwaraP51500080743Harsool2025Active31 Dec 2030—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sara Swapnangan - A4, A5, A6 BuildingsOn date
  • Sara MetrovilleOn date
  • Sara Metroville+12 mo
  • Sara MetrovilleOn date
  • Sara Swapnangan - Row HousesOn date
  • Sara Swapnangan Phase-2, H-1, H-2 And G Type Row HouseOn date
  • Sara Angan B2, B3, C1 And C2 Type Building+45 mo
  • Sara Angan Phase-1 A1 -B1 Type BuildingOn date
  • Sara Swarajya Phase-IOn date
  • Sara NiwaraOn date

Track record notes

  • 6 of 8 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 45 months, for Sara Angan B2, B3, C1 And C2 Type Building (P51500032885).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology