Company or firm · 3 projects · 4 MahaRERA registrations

Projects34 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Indrayani VatikaP52100010977Dehu2017Not reported30 Dec 2023—On date
Indrayani VatikaP52100028191Dehu2021Not reported30 Dec 2022—On date
Indrayani VatikaP52100032443Dehu2022Not reported30 Jun 202430 Jun 2025+12 months
Anandi ViharP52100053434Dehu2023Not reported31 Dec 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Indrayani VatikaOn date
  • Indrayani VatikaOn date
  • Indrayani Vatika+12 mo
  • Anandi ViharOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Indrayani Vatika (P52100032443).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.