Saikedareshwar Developers Llp

Company or firm · 2 projects · 5 MahaRERA registrations

2Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sai Nagari Phase IIIP52100052837Pune (M Corp.)2023Certificate Signed28 May 202928 Sep 2029+4 months
Sai NagariP52100052977Katraj2023Certificate Signed28 May 202928 Sep 2029+4 months
Sai NagariP52100052996Katraj2023Certificate Signed28 May 202928 Sep 2029+4 months
Sai NagariP52100078517Katraj2024Certificate Signed31 Dec 202930 Apr 2030+4 months
Sai NagariPM1264042502917Katraj2026Not reported31 Dec 2030—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sai Nagari Phase III+4 mo
  • Sai Nagari+4 mo
  • Sai Nagari+4 mo
  • Sai Nagari+4 mo
  • Sai NagariOn date

Track record notes

  • Longest extension on record: 4 months, for Sai Nagari Phase III (P52100052837).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology