Ravima Developer

Company or firm · 2 projects · 3 MahaRERA registrations

Projects23 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
The Work ClubP52100021171Pimpri Chinchawad (M Corp.)2019Not reported30 Apr 2023—On date
The Work ClubP52100027555Pimpri Chinchawad (M Corp.)2020Not reported30 Jun 202430 Jun 2025+12 months
Newton Homes Hadapsar Near Runwal Seagull Phase IP52100048243Pune City2022Not reported30 Sep 2025—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • The Work ClubOn date
  • The Work Club+12 mo
  • Newton Homes Hadapsar Near Runwal Seagull Phase IOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for The Work Club (P52100027555).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology