Raghukul Constructions Pvt. Ltdd
Company or firm · 5 projects · 5 MahaRERA registrations · 3 reported completed
Also appears as Raghukul Constructions Private Limited
5Projects5 RERA registrations
3Completedas reported on MahaRERA project pages
100%Kept RERA date4 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Amrit SaritaP50500001628 | Nagpur (M Corp.) | 2017 | Completed | 31 Dec 2019 | — | On date |
| Amrit KalashP50500001929 | Nagpur (M Corp.) | 2017 | Completed | 31 Mar 2019 | — | On date |
| Kanchan GeetP50500018334 | Nagpur (M Corp.) | 2018 | Completed | 30 Dec 2024 | — | On date |
| Silver ParadiseP50500023454 | Nagpur (M Corp.) | 2019 | Certificate Signed | 30 Dec 2026 | 30 Dec 2026 | On date |
| Sri BalajiP50500034108 | Nagpur (M Corp.) | 2022 | Certificate Signed | 26 Jan 2026 | 26 Jan 2026 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology