Pravin Keshav Badhekar

Individual promoter · 15 projects · 15 MahaRERA registrations

15Projects15 RERA registrations
0Completedas reported on MahaRERA project pages
25%Kept RERA date2 of 8 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 9 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Samruddhi ResidencyP52100006236Pune (M Corp.)2017Certificate Signed5 Jul 201915 Feb 2023+43 months
Vinayak15P52100007478Kothrud2017Certificate Signed9 Nov 20219 Nov 2021On date
MrudgandhaP52100029764Kothrud2021Certificate Signed31 Dec 202431 Dec 2025+12 months
DwarkaP52100029936Kothrud2021Certificate Signed31 Dec 202431 Dec 2025+12 months
Rising HillsP52100033495Bavdhan Kh.2022Certificate Signed31 Mar 202531 Aug 2026+17 months
RamchandraP52100034646Kothrud2022Certificate Signed30 Sep 202430 Sep 2025+12 months
Tungabhadra Co Op Hsg SocP52100046370Kothrud2022Certificate Signed30 Apr 202531 Aug 2026+16 months
NeerajP52100050106Kothrud2023Certificate Signed31 Aug 202731 Dec 2027+4 months
KrushnakunjP52100050407Kothrud2023Certificate Signed21 Dec 202521 Dec 2025On date
Nirmitee HeightsP52100077284Kothrud2024Certificate Signed31 Dec 202731 Dec 2027On date
ShyamalprabhaP52100077390Kothrud2024Certificate Signed31 Dec 202731 Dec 2027On date
Ankur HeightsP52100080105Kothrud2025Certificate Signed30 Jun 202830 Oct 2028+4 months
BhaveshP52100080230Parvati2025Certificate Signed31 Mar 202931 Mar 2029On date
Anand TerracePM1260002500913Kothrud2025Certificate Signed30 Sep 202930 Jan 2030+4 months
Badhekar HorizonPM1260002501143Kothrud2025Certificate Signed31 Dec 203031 Dec 2030On date
Show all 15 registrationsShow fewer

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Samruddhi Residency+43 mo
  • Vinayak15On date
  • Mrudgandha+12 mo
  • Dwarka+12 mo
  • Rising Hills+17 mo
  • Ramchandra+12 mo
  • Tungabhadra Co Op Hsg Soc+16 mo
  • Neeraj+4 mo
  • KrushnakunjOn date
  • Nirmitee HeightsOn date
Show all 15 registrations
  • ShyamalprabhaOn date
  • Ankur Heights+4 mo
  • BhaveshOn date
  • Anand Terrace+4 mo
  • Badhekar HorizonOn date

Track record notes

  • 2 of 8 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 43 months, for Samruddhi Residency (P52100006236).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology