Prakash Pandurang Chavan

Individual promoter · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+48 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sai Velocity IIP52100003410Bavadhan Bk2017Certificate Signed25 Dec 201930 Dec 2027+96 months
Sai Velocity IP52100003671Bavadhan Bk2017Certificate Signed31 Dec 201731 Dec 2017On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sai Velocity II+96 mo
  • Sai Velocity IOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 96 months, for Sai Velocity II (P52100003410).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology