1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
EKTA CO. OP. HSG. SOC. PropP51800024202Greater Mumbai (M Corp.) (Part) (802794)2020Lapsed30 Dec 202430 Jun 2025+6 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • EKTA CO. OP. HSG. SOC. Prop+6 mo

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 6 months, for EKTA CO. OP. HSG. SOC. Prop (P51800024202).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology