Peninsula Land Limited
Company or firm · 11 projects · 17 MahaRERA registrations
Projects1117 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date83%10 of 12 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 2 extended
Regulatory cases1MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Celestia SpacesP51900005432 | Ward Fsouth | 2017 | Not reported | 30 Jun 2021 | 30 Dec 2022 | +18 months |
| addressOneP52100015747 | Gahunje | 2018 | Not reported | 30 Apr 2023 | — | On date |
| addressOneP52100015756 | Gahunje | 2018 | Not reported | 30 Dec 2022 | — | On date |
| addressOneP52100015779 | Gahunje | 2018 | Not reported | 30 May 2023 | — | On date |
| addressOneP52100015803 | Gahunje | 2018 | Not reported | 28 Aug 2023 | — | On date |
| addressOneP52100018788 | Gahunje | 2018 | Not reported | 30 Jun 2026 | — | On date |
| addressOneP52100018855 | Gahunje | 2018 | Not reported | 30 Dec 2023 | 29 Dec 2024 | +12 months |
| SERENITY at Ashok AstoriaP51600033661 | Govardhan | 2022 | Not reported | 31 Mar 2026 | — | On date |
| Peninsula AshokVannP52100046842 | Gahunje | 2022 | Not reported | 30 Apr 2024 | — | On date |
| Peninsula AshokVannP52100046962 | Gahunje | 2022 | Not reported | 30 Jun 2023 | — | On date |
| Peninsula AshokVannP52100046963 | Gahunje | 2022 | Not reported | 30 Jun 2024 | — | On date |
| Peninsula Centre Commercial Building Shopping ComplexP52100077072 | Gahunje | 2024 | Not reported | 31 Jul 2026 | — | On date |
| AshokVistas by Peninsula Land - Phase 2P52100078539 | Mawal | 2024 | Not reported | 30 Jun 2027 | — | On date |
| AshokVistas by Peninsula Land Phase 1P52100078661 | Gahunje | 2025 | Not reported | 31 Dec 2026 | — | On date |
| Peninsula PlazaPC1260002500274 | Gahunje | 2025 | Not reported | 31 Mar 2028 | — | On date |
| Ashok Villas ImperialPR1260002600608 | Gahunje | 2026 | Not reported | 31 Dec 2029 | — | On date |
| Ashok Villas GrandePR1260002600614 | Gahunje | 2026 | Not reported | 31 Dec 2029 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 10 of 12 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 18 months, for Celestia Spaces (P51900005432).
Regulatory cases across projects
- DeregisteredDeregistered: SERENITY at Ashok Astoria · SERENITY at Ashok Astoria · P51600033661
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology