Company or firm · first RERA registration 2017
Pagarani Universal Infrastructure Pvt Ltd
Of 2 registrations whose promised date has arrived, 1 were never extended past it (50%). When extended, the date moved a median 12 mo — longer than Maharashtra's 4 mo.
Projects33 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay12 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
1 registration of 3 moved past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Universal CubicalP51800002157 | Andheri | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Universal Paradise A And BP51800003121 | Andheri | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Universal Garden- B WingP51800017902 | Andheri | Certificate Signed | 30 Dec 2026 | 30 Dec 2026 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology
