Company or firm · first RERA registration 2017

Pagarani Universal Infrastructure Pvt Ltd

Of 2 registrations whose promised date has arrived, 1 were never extended past it (50%). When extended, the date moved a median 12 mo — longer than Maharashtra's 4 mo.

Projects33 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay12 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record

1 registration of 3 moved past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Universal CubicalP51800002157AndheriCertificate Signed31 Dec 201831 Dec 2019+12 mo
Universal Paradise A And BP51800003121AndheriCertificate Signed31 Dec 201831 Dec 2018On date
Universal Garden- B WingP51800017902AndheriCertificate Signed30 Dec 202630 Dec 2026On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology