Osho Developers

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Ankur PalaceP51800010439Borivali2017Not reported15 Aug 201914 Feb 2021+18 months
Neelkamal HeightsP51800009687Borivali2017Not reported31 Dec 2017—On date
Sai Krupa Chsl RedevelopedP51800034596Borivali2022Not reported30 Jun 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Ankur Palace+18 mo
  • Neelkamal HeightsOn date
  • Sai Krupa Chsl RedevelopedOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Ankur Palace (P51800010439).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology