Sai Krupa Chsl Redeveloped

Certificate Signed

Borivali, Mumbai Suburban 400091 |Promoter: OSHO Developers

11 Apr 2022Registered with MahaRERA
30 Jun 2026Promised completion
1Building
102Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
—102 units in all
Address
298, 301, Ram Mandir Road, BABHAIPIN 400091
Designated bank account
179
Developed in phases
No

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Jun 2026

The latest completion date on record passed 4 months ago.

Registered
11 Apr 2022
Promised
30 Jun 2026

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5180003459611 Apr 202230 Jun 202630 Jun 2026OSHO DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Sai Krupa Chsl29102

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

102 units registered

— · 102 units
TypeCarpet areaUnits
——102

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 152 filings listed on MahaRERA's project page

Extension certificate

Registration certificate

Finance

  • PAN CardPan Card OD.pdf · uploaded 14 Feb 2022Source

Legal

  • Declaration Form BForm B.pdf · uploaded 15 Feb 2022Source
  • Legal Title reportTitle Clearance Certificate.pdf · uploaded 10 Mar 2022Source

Migrated

  • 1 PAN CardPan Card OD.pdf · uploaded 14 Feb 2022Source
  • 1 Details of encumbrancesEncumberances.pdf · uploaded 14 Feb 2022Source
  • 1 Copy of Layout Approval (in case of layout)Layout Declaration.pdf · uploaded 14 Feb 2022Source
Show all 154 documentsShow fewer documents

Migrated

  • 1 CERSAI detailsCERSAI_Search_Report For_Asset_Based_Search.pdf · uploaded 14 Feb 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentIOD Plans Page 1.pdf · uploaded 15 Feb 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentIOD Page 2.pdf · uploaded 15 Feb 2022Source
  • 3 Building Plan Approval / NA Order for plotted developmentIOD Page 3.pdf · uploaded 15 Feb 2022Source
  • 4 Building Plan Approval / NA Order for plotted developmentIOD Page 4.pdf · uploaded 15 Feb 2022Source
  • 5 Building Plan Approval / NA Order for plotted developmentIOD Page 5.pdf · uploaded 15 Feb 2022Source
  • 6 Building Plan Approval / NA Order for plotted developmentIOD Page 6.pdf · uploaded 15 Feb 2022Source
  • 7 Building Plan Approval / NA Order for plotted developmentIOD Page 7.pdf · uploaded 15 Feb 2022Source
  • 8 Building Plan Approval / NA Order for plotted developmentIOD Page 8.pdf · uploaded 15 Feb 2022Source
  • 9 Building Plan Approval / NA Order for plotted developmentIOD Page 9.pdf · uploaded 15 Feb 2022Source
  • 10 Building Plan Approval / NA Order for plotted developmentIOD Page 10.pdf · uploaded 15 Feb 2022Source
  • 11 Building Plan Approval / NA Order for plotted developmentIOD Page 11.pdf · uploaded 15 Feb 2022Source
  • 12 Building Plan Approval / NA Order for plotted developmentIOD Page 12.pdf · uploaded 15 Feb 2022Source
  • 13 Building Plan Approval / NA Order for plotted developmentIOD Page 13.pdf · uploaded 15 Feb 2022Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 15 Feb 2022Source
  • 1 Proforma of Allotment letterDeclaration_Allotment Letter.pdf · uploaded 15 Feb 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Certificate dated 12-02-2022.pdf · uploaded 16 Feb 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certifiate_Saikrupa.pdf · uploaded 16 Feb 2022Source
  • 1 Copy of the legal title reportTitle Clearance Certificate.pdf · uploaded 10 Mar 2022Source
  • 1 Declaration about Commencement CertificateCOMMENCEMENT CERTIFICATE.pdf · uploaded 10 Mar 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC 01042022.pdf · uploaded 1 Apr 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final CA Certificate -RERA New format Signed.pdf · uploaded 1 Apr 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architechs Certificate.pdf · uploaded 8 Jul 2022Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER'S CERTIFICATE.pdf · uploaded 8 Jul 2022Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 3 Nov 2022Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 3 Nov 2022Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Sai Krupa CHSL.pdf · uploaded 21 Nov 2022Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Cert II Qtr 2022.pdf · uploaded 5 Jan 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engn Cert II Qtr 2022.pdf · uploaded 5 Jan 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Cert II Qtr 2022.pdf · uploaded 5 Jan 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)osho ca certificate.pdf · uploaded 16 Jan 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Certificate dated 30122022.pdf · uploaded 9 Feb 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect form 1.pdf · uploaded 9 Feb 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect form 1.pdf · uploaded 9 Feb 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer form 2.pdf · uploaded 9 Feb 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer form 2.pdf · uploaded 9 Feb 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Sai Krupa 31122022.pdf · uploaded 9 Feb 2023Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Sales_28022023.pdf · uploaded 28 Feb 2023Source
  • 2 Copy of Layout Approval (in case of layout)Revised Approved drawing_1-1.pdf · uploaded 17 May 2023Source
  • 3 Copy of Layout Approval (in case of layout)Revised Approved drawing_2-2.pdf · uploaded 17 May 2023Source
  • 4 Copy of Layout Approval (in case of layout)Revised Approved drawing_3-3.pdf · uploaded 17 May 2023Source
  • 5 Copy of Layout Approval (in case of layout)Revised Approved drawing_4-4.pdf · uploaded 17 May 2023Source
  • 6 Copy of Layout Approval (in case of layout)Revised Approved drawing_5-5.pdf · uploaded 17 May 2023Source
  • 7 Copy of Layout Approval (in case of layout)Revised Approved drawing_6-6.pdf · uploaded 17 May 2023Source
  • 8 Copy of Layout Approval (in case of layout)Revised Approved drawing_7-7.pdf · uploaded 17 May 2023Source
  • 9 Copy of Layout Approval (in case of layout)Revised Approved drawing_8-8.pdf · uploaded 17 May 2023Source
  • 10 Copy of Layout Approval (in case of layout)Revised Approved drawing_9-9.pdf · uploaded 17 May 2023Source
  • 11 Copy of Layout Approval (in case of layout)Revised Approved drawing_10-10.pdf · uploaded 17 May 2023Source
  • 12 Copy of Layout Approval (in case of layout)Revised Approved drawing_11-11.pdf · uploaded 17 May 2023Source
  • 13 Copy of Layout Approval (in case of layout)Revised Approved drawing_12-12.pdf · uploaded 17 May 2023Source
  • 14 Copy of Layout Approval (in case of layout)Revised Approved drawing_13-13.pdf · uploaded 17 May 2023Source
  • 15 Copy of Layout Approval (in case of layout)Revised Approved drawing_14-14.pdf · uploaded 17 May 2023Source
  • 16 Copy of Layout Approval (in case of layout)Revised Approved drawing_15-end.pdf · uploaded 17 May 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentFurther CC May 2023.pdf · uploaded 17 May 2023Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate March 2023 DSC.pdf · uploaded 24 May 2023Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Structural Certificate March 2023 DSC (1).pdf · uploaded 25 May 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed CA Certificate March'23 DSC.pdf · uploaded 25 May 2023Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 3 Aug 2023Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 3 Aug 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 3 Aug 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)SIGNED FORM 5 FY 22-23.pdf · uploaded 29 Sep 2023Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 19 Oct 2023Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 19 Oct 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 19 Oct 2023Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate Dec 23.pdf · uploaded 30 Jan 2024Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate Dec 23.pdf · uploaded 30 Jan 2024Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Ca Certificate Dec 23.pdf · uploaded 30 Jan 2024Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Certificate Sai Krupa CHSL Mar'24.pdf · uploaded 13 Apr 2024Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engn's Certficate Shic Krupa CHSL Mar'24.pdf · uploaded 13 Apr 2024Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Sai Krupa CHSL Mar'24 (1).pdf · uploaded 13 Apr 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentPart OC.pdf · uploaded 13 Apr 2024Source
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 19 Jul 2024Source
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 19 Jul 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)form 2A.pdf · uploaded 19 Jul 2024Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 19 Jul 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 24 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 24 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 24 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form 5 23-24.pdf · uploaded 24 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 21 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 21 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 21 Jan 2025Source
  • Form 5 (FY 2024-2025)CA Form 5_ 24-25 Annual .pdf · uploaded 30 Sep 2025Source
  • Withdrawal Update Form 1Arch Cert 1st Qtr.pdf · uploaded 22 Dec 2025Source
  • Withdrawal Update Form 1Arch Cert2nd Qtr 2025 26.pdf · uploaded 22 Dec 2025Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 22 Dec 2025Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 22 Dec 2025Source
  • Withdrawal Update Form 3CA Cert 1st Qtr 2025 26.pdf · uploaded 22 Dec 2025Source
  • Withdrawal Update Form 3CA Certificate 2nd Qtr 2025 26.pdf · uploaded 22 Dec 2025Source
  • Withdrawal Update Form 1Aech Cert_3rd Qtr 2025 26.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 1Aech Cert_3rd Qtr 2025 26.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 2Engn Cert 3nd Qtr 2025 26.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 2Engn Cert 3nd Qtr 2025 26.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 3CA_Certificate_3rd Qtr 2025 26.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 3CA_Certificate_3rd Qtr 2025 26.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 1form 1.pdf · uploaded 26 May 2026Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 26 May 2026Source
  • Withdrawal Update Form 3form 3.pdf · uploaded 26 May 2026Source
  • Withdrawal Update Form 1form 1.pdf · uploaded 21 Jul 2026Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 21 Jul 2026Source
  • Withdrawal Update Form 3CA_Certificate_3rd Qtr 2025 26.pdf · uploaded 21 Jul 2026Source
  • Form 2A (FY 2025-2026)Site Super Certificate 2A.pdf · uploaded 21 Jul 2026Source
  • Occupational CertificateOC.pdf · uploaded 21 Jul 2026Source
  • Occupational CertificateOC plans 1-5.pdf · uploaded 21 Jul 2026Source
  • Occupational CertificateOC plans 6-10.pdf · uploaded 21 Jul 2026Source
  • Occupational CertificateOC plans 11-end.pdf · uploaded 21 Jul 2026Source

Technical

  • DocumentLayout Declaration.pdf · uploaded 14 Feb 2022Source
  • DocumentIOD Plans Page 1.pdf · uploaded 15 Feb 2022Source
  • DocumentIOD Page 2.pdf · uploaded 15 Feb 2022Source
  • DocumentIOD Page 3.pdf · uploaded 15 Feb 2022Source
  • DocumentIOD Page 4.pdf · uploaded 15 Feb 2022Source
  • DocumentIOD Page 5.pdf · uploaded 15 Feb 2022Source
  • DocumentIOD Page 6.pdf · uploaded 15 Feb 2022Source
  • DocumentIOD Page 7.pdf · uploaded 15 Feb 2022Source
  • DocumentIOD Page 8.pdf · uploaded 15 Feb 2022Source
  • DocumentIOD Page 9.pdf · uploaded 15 Feb 2022Source
  • DocumentIOD Page 10.pdf · uploaded 15 Feb 2022Source
  • DocumentIOD Page 11.pdf · uploaded 15 Feb 2022Source
  • DocumentIOD Page 12.pdf · uploaded 15 Feb 2022Source
  • DocumentIOD Page 13.pdf · uploaded 15 Feb 2022Source
  • DocumentRevised Approved drawing_1-1.pdf · uploaded 17 May 2023Source
  • DocumentRevised Approved drawing_2-2.pdf · uploaded 17 May 2023Source
  • DocumentRevised Approved drawing_3-3.pdf · uploaded 17 May 2023Source
  • DocumentRevised Approved drawing_4-4.pdf · uploaded 17 May 2023Source
  • DocumentRevised Approved drawing_5-5.pdf · uploaded 17 May 2023Source
  • DocumentRevised Approved drawing_6-6.pdf · uploaded 17 May 2023Source
  • DocumentRevised Approved drawing_7-7.pdf · uploaded 17 May 2023Source
  • DocumentRevised Approved drawing_8-8.pdf · uploaded 17 May 2023Source
  • DocumentRevised Approved drawing_9-9.pdf · uploaded 17 May 2023Source
  • DocumentRevised Approved drawing_10-10.pdf · uploaded 17 May 2023Source
  • DocumentRevised Approved drawing_11-11.pdf · uploaded 17 May 2023Source
  • DocumentRevised Approved drawing_12-12.pdf · uploaded 17 May 2023Source
  • DocumentRevised Approved drawing_13-13.pdf · uploaded 17 May 2023Source
  • DocumentRevised Approved drawing_14-14.pdf · uploaded 17 May 2023Source
  • DocumentRevised Approved drawing_15-end.pdf · uploaded 17 May 2023Source
  • DocumentPlans 1.pdf · uploaded 27 Feb 2026Source
  • DocumentPlans 2-3.pdf · uploaded 27 Feb 2026Source
  • DocumentPlans 4-5.pdf · uploaded 27 Feb 2026Source
  • DocumentPlans 6.pdf · uploaded 27 Feb 2026Source
  • DocumentPlans 7.pdf · uploaded 27 Feb 2026Source
  • DocumentPlans 8.pdf · uploaded 27 Feb 2026Source
  • DocumentPlans 9.pdf · uploaded 27 Feb 2026Source
  • DocumentPlans 10-11.pdf · uploaded 27 Feb 2026Source
  • DocumentPlans 12.pdf · uploaded 27 Feb 2026Source
  • DocumentPlans 13.pdf · uploaded 27 Feb 2026Source
  • DocumentPlans 14.pdf · uploaded 27 Feb 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Borivali, Borivali taluka

Survey, CTS, gat or plot numbers

298301

Boundaries

North
Ram Mandir Road
South
299 300 302
East
304
West
297 296

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectKalpesh Shah—
ArchitectTriarch Design Studio—
Chartered accountantJagdish M Parekh—
EngineerSamarth Agarwal—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology