Om Shivam Buildcon Private Limited

Company or firm · 10 projects · 11 MahaRERA registrations · 3 reported completed

10Projects11 RERA registrations
3Completedas reported on MahaRERA project pages
80%Kept RERA date8 of 10 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 3 extended
2Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shiv Elite Phase IIIP50500005732Shankarpur2017Certificate Signed27 Jul 201927 Jul 2019On date
Shiv BrightonP50500006203Panjari Farm2017Completed31 Jan 2021—On date
Shiv BrightonP50500006295Panjari Farm2017Completed31 Jan 2021—On date
Shiv Elite Phase IIP50500007132Shankarpur2017Certificate Signed31 Jul 201831 Jul 2018On date
Shiv Elite Phase IVP50500009553Shankarpur2017Certificate Signed27 Jan 202127 Jan 2021On date
Shiv Elite Phase IP50500009639Shankarpur2017Certificate Signed31 Jul 201831 Jul 2018On date
Shiv Elite Phase IV GeraniumP50500017835Shankarpur2018Certificate Signed28 Aug 202228 Aug 2022On date
Shiv Kailasa Phase IP50500018424Sondapar2018Completed1 Oct 2024—On date
Shiv Brighton Phase IVP50500024193Panjari Farm2020Certificate Signed30 Jan 202429 Jan 2025+12 months
Shiv Brighton Phase IIIP50500024271Panjari Farm2020Certificate Signed30 Jan 202429 Jan 2025+12 months
Shiv Kailasa Phase IIP50500029945Sondapar2021Certificate Signed25 Dec 202625 Apr 2027+4 months
Show all 11 registrationsShow fewer

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shiv Elite Phase IIIOn date
  • Shiv BrightonOn date
  • Shiv BrightonOn date
  • Shiv Elite Phase IIOn date
  • Shiv Elite Phase IVOn date
  • Shiv Elite Phase IOn date
  • Shiv Elite Phase IV GeraniumOn date
  • Shiv Kailasa Phase IOn date
  • Shiv Brighton Phase IV+12 mo
  • Shiv Brighton Phase III+12 mo
Show all 11 registrations
  • Shiv Kailasa Phase II+4 mo

Track record notes

  • 8 of 10 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Shiv Brighton Phase IV (P50500024193).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology