Nyati Construction Private Limited

Company or firm · 3 projects · 6 MahaRERA registrations

3Projects6 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Nyati EraP52100032682Haveli2022Not reported8 Aug 2025—On date
Nyati EraP52100035037Haveli2022Not reported31 Mar 202530 Sep 2025+6 months
Nyati EraP52100047727Haveli2022Not reported30 Nov 2026—On date
Nyati EmblemP52100076789Parvati2024Not reported31 Dec 2027—On date
Nyati EvaniaP52100078605Parvati2024Not reported30 Apr 2029—On date
Nyati EraPR1263032500175Haveli2025Not reported30 Jun 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Nyati EraOn date
  • Nyati Era+6 mo
  • Nyati EraOn date
  • Nyati EmblemOn date
  • Nyati EvaniaOn date
  • Nyati EraOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 6 months, for Nyati Era (P52100035037).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology