Nirmaan Infra

Company or firm · 2 projects · 3 MahaRERA registrations

2Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Central Heights 1P50500051265Pipla2023Active31 Dec 2028—On date
Central HeightsP50500053562Pipla2023Certificate Signed31 Dec 202830 Apr 2029+4 months
Central HeightsP50500053730Pipla2023Certificate Signed31 Dec 202830 Apr 2029+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Central Heights 1On date
  • Central Heights+4 mo
  • Central Heights+4 mo

Track record notes

  • Longest extension on record: 4 months, for Central Heights (P50500053562).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology