MKY Infrastructure

Company or firm · 1 project · 2 MahaRERA registrations

1Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+7 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
DharmaviharP51700010249Bhiwandi (M Corp.)2017Certificate Signed31 Jul 201830 Apr 2019+9 months
DharmaviharP51700019748Bhiwandi (M Corp.)2019Certificate Signed31 Mar 202731 Jul 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Dharmavihar+9 mo
  • Dharmavihar+4 mo

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 9 months, for Dharmavihar (P51700010249).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology