Company or firm · first RERA registration 2017
Mauli Sai Developers Pvt Ltd
Of 2 registrations whose promised date has arrived, 0 were never extended past it (0%).
Projects44 RERA registrations
Kept RERA date0%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
3 registrations of 4 moved past the RERA date
Months late against the original RERA promise, per registration
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Mauli OmkarP51800001198 | Borivali | Certificate Signed | 8 Jul 2023 | 7 Jul 2027 | +48 mo |
| Mauli PrideP51800001199 | Borivali | Certificate Signed | 8 Jul 2024 | 8 Jul 2027 | +36 mo |
| Mauli DesireP51800001946 | Borivali | Certificate Signed | 29 Jun 2028 | 29 Jun 2028 | On date |
| Mauli Pride 1 BcdePM1181012502549 | Kurar | Certificate Signed | 30 Dec 2028 | 30 Apr 2029 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology