Company or firm · first RERA registration 2017

Mauli Sai Developers Pvt Ltd

Of 2 registrations whose promised date has arrived, 0 were never extended past it (0%).

Projects44 RERA registrations
Kept RERA date0%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record

3 registrations of 4 moved past the RERA date

Months late against the original RERA promise, per registration

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Mauli OmkarP51800001198BorivaliCertificate Signed8 Jul 20237 Jul 2027+48 mo
Mauli PrideP51800001199BorivaliCertificate Signed8 Jul 20248 Jul 2027+36 mo
Mauli DesireP51800001946BorivaliCertificate Signed29 Jun 202829 Jun 2028On date
Mauli Pride 1 BcdePM1181012502549KurarCertificate Signed30 Dec 202830 Apr 2029+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology