Skip to content

Magniton Infra

Company or firm · 1 project · 1 MahaRERA registration · 1 reported completed

1Projects1 RERA registration
1Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
The AddressP50500012771Nagpur (M Corp.)2017Completed31 Mar 2018—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • The AddressOn date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology