M K Patil Developers
Company or firm · 5 projects · 5 MahaRERA registrations · 1 reported completed
5Projects5 RERA registrations
1Completedas reported on MahaRERA project pages
40%Kept RERA date2 of 5 past their proposed date, not extended
+24 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Wing D- DurvankurP51700004981 | Badlapur (M Cl) | 2017 | Certificate Signed | 19 Aug 2019 | 31 Dec 2023 | +52 months |
| Wing B-6 SwanandP51700008565 | Badlapur (M Cl) | 2017 | Completed | 31 Dec 2018 | — | On date |
| Wing C-7 MoryaP51700008767 | Badlapur (M Cl) | 2017 | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Wing C-5 GajmukhP51700017758 | Badlapur (M Cl) | 2018 | Certificate Signed | 31 Dec 2019 | 30 Dec 2022 | +36 months |
| Wing B4 LambodarP51700018374 | Badlapur (M Cl) | 2018 | Certificate Signed | 30 Jun 2020 | 29 Jun 2022 | +24 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 52 months, for Wing D- Durvankur (P51700004981).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology