Company or firm · 3 projects · 3 MahaRERA registrations · 2 reported completed

Projects33 RERA registrations
Completed2as reported on MahaRERA project pages
Kept RERA date100%3 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases1MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
TulipP50500001330Nagpur (M Corp.)2017Completed31 Mar 2019—On date
AsterP50500001906Bokhara2017Completed30 Sep 2020—On date
Leverage Greenwoods - UnityP50500031612Pipla2021Not reported31 Dec 2025—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • TulipOn date
  • AsterOn date
  • Leverage Greenwoods - UnityOn date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.

Regulatory cases across projects